Biotube ProPak and LOS Pump Package Installation Manual
Step 8. Test Float Switches and Control Panel, cont.
Step 8c:
Snap the float switch assembly back into the bracket.
• Make sure the float switches can move freely up and down without
interference from each other or contact with the vault wall.
• For settings or adjustments, see NIN-MF-DA-1,
.
Step 8d:
Neatly coil the float switch cords and secure them in the riser.
• Make sure the coils don’t tangle with the float switches.
Step 8e:
Place the “Auto/Off/Man” switch on the control panel to “Auto,”
make sure the control panel circuit breakers are in the “On” position, and
close the control panel door.
Step 9. Complete the Installation
Step 9a:
Check the pump package, connections, fittings, and other
components for correct, completed installation and accessibility.
Step 9b:
Secure the access lids on the tank.
Step 9c:
Finish backfilling the tank excavation, transport/service lines,
and electrical conduit runs, if those tasks are not yet done. Follow the
manufacturer’s and engineer’s instructions.
8c
Stem
Tee
Tee level
with bracket
Float
bracket
Attach the assembly to the bracket, level with the bracket.
Installation Steps