Installing the Switch
19
Fabric card fillers have IPMB controllers and fans, but no switch chips. This design
enables the filler to assist with removing heat from the chassis. The fabric card filler
is enabled and activated like a fabric card.
Related Information
■
“Install the Fabric Cards or Fabric Card Fillers” on page 67
■
“Install the Line Cards or Line Card Fillers” on page 72
Installation Preparation
Before installing or servicing the switch, you must prepare the following:
■
The environment where the switch is to be installed must conform to the
requirements found in
“Environmental Requirements” on page 3
■
The rack to receive the switch must have proper power, management, and
InfiniBand fabric cabling brought to it.
■
The rack must have an available location for the switch.
■
There must be a clean, dry, stable work surface.
Related Information
■
“Preparing the Chassis” on page 29
Suggested Tools for Installation
The following tools are necessary or beneficial for installing the switch:
■
Socket extension
■
10 mm Socket
■
20 mm Socket
■
Ratchet
■
Pen
■
Notepad
■
No. 2 Phillips screwdriver
■
Flashlight
■
Gloves
■
Magnifying glass
■
Other tools
Содержание Sun Datacenter InfiniBand Switch 648
Страница 1: ...Sun Datacenter InfiniBand Switch 648 Installation Guide Part No 820 7738 12 May 2010 Revision A ...
Страница 8: ...viii Sun Datacenter InfiniBand Switch 648 Installation Guide May 2010 ...
Страница 134: ...124 Sun Datacenter InfiniBand Switch 648 Installation Guide May 2010 ...
Страница 140: ...130 Sun Datacenter InfiniBand Switch 648 Installation Guide May 2010 ...