Preparing the Site
37
FIGURE:
5-Wire Power Cord AC Receptacle
Related Information
■
“Power Cord Specifications” on page 32
■
“Facility Power Requirements” on page 37
■
“Power Cord-to-Power Supply Relationship” on page 40
Facility Power Requirements
The server is designed to be powered by two utility power grids. Connect three
power cords (AC0, AC1, and AC2) to one power grid, and connect the remaining
three power cords to a second power grid (AC3, AC4, and AC5). All six power cords
must be connected when operating the server.
Figure Legend
1
L1
2
L2
3
L3
4
Neutral
5
Ground
Содержание sparc M5-32
Страница 1: ...SPARC M5 32 and SPARC M6 32 Servers Installation Guide Part No E41215 05 December 2014 ...
Страница 8: ...viii SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 ...
Страница 16: ...6 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 Front Components ...
Страница 18: ...8 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 Rear Components ...
Страница 21: ...Understanding the Server 11 FIGURE DCU Locations Rear of Server ...
Страница 43: ...Preparing the Site 33 FIGURE 4 Wire Power Cord AC Plug 460P9W Figure Legend 1 L1 2 L2 3 L3 4 Ground ...
Страница 51: ...Preparing the Site 41 ...
Страница 82: ...72 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 ...
Страница 106: ...96 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 ...
Страница 182: ...172 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 ...