Version 1.2.8 - 2020-08-03
27
Translation of original operating manual
MT50
GB
MT
5
0_GB
_3.
fm
4.3.6 Functional test
Check if all fixing screws of the milling-machine are tightened.
Check if the clamping screw for slewing as well as the fixing screw of the milling head is
well tightened.
Check if all spindles are running smoothly.
4.3.7
Check the filling level of the gear oil
The milling-machine is delivered with gear oil.
Check the filling levels of the gear vertical milling and of the infeed of the X axis.
Fill the container of the gearboxes over the filling port with a standard gear oil.
„Img.6-6: Filler hole vertical gear“ on page 50
„Img.6-8: Filler hole feed gear“ on page 51
4.3.8
Refill coolant lubricant
The milling-machine is delivered without coolant lubricant.
Fill in coolant.
ATTENTION!
Failure of the pump in case of dry running. The pump is lubricated by the coolant. Do not
start up the pump without cooling agent.
Coolant lubricant system on page 20
4.4
Electrical connection
CAUTION!
Install the connection cable of the machine in such a way that people will not stumble
over it.
The machine is installed and ready to operate. Please check that the type of current, voltage
and protection fuse correspond to the values specified. A protective earth ground wire connec-
tion must be available. Main Fuse 16A.
Make sure that the existing power supply matches the drilling-milling machine.
The drilling-milling machine must be correctly earthed.
Press the push button for clockwise.
Then the spindle must turn clockwise.
When looking from the top of the machine the spindle must rotate clockwise.
If it rotates anticlockwise two of the three phase conductors must be exchanged.
WARNING!
Works on the electrical equipment must only be performed by an electrical specialist
according to the electro-technical rules.
4.5
First commissioning
The machine may only be commissioned after proper installation.
WARNING!
First commissioned of the milling machine by inexperienced personnel constitute a risk
to personnel and equipment. We do not accept any liability for damages caused by
incorrectly performed commissioning.