Document No.: IM-1508 

Revision Level: 03 

Approval Date: 10-JUNE-2020 

Author: T. Robinson/C Fisher 

Approved By: C. Fisher 

 

 

Hero

 40 Amp Tap Commander 

Installation Guide 

The 40 Amp 

Tap Commander ™ connects to the Rectifier and 

Hero 1 or Hero 2 Rectifier Monitor and 

allows the user to adjust the output voltage of the rectifier locally, remotely via OmniView or 
automatically to keep the rectifier output current relatively constant. 

1.

 

Verify the following components are included in the package and are free from damage: 

 

Tap Commander Module 

 

Tap Commander Interface Cable (6’)

 

 

Tap Power Cable 

 

14 Yellow Tap Wires 

 

Snap-Track (for mounting the Tap Commander) 

 

Installation Instructions 

2.

 

Before installing the Tap Commander: 

 

Using a multimeter, measure and record the Shunt Voltage  

 

Using a multimeter, measure and record the Output Voltage 

 

Using a multimeter, find and mark two Taps that measure 11-15 VAC between them. These 
will be Power Taps for the 40 Amp Tap Commander. 

 

Install the Hero RMU (see installation guide included with the Hero) 

 

 

During the installation of the Hero, route the Tap Commander Accessory cable through the 
conduit. See the note on the next page if you must cut the 4 pin connector off. 

 

Make sure the current protection wires are firmly screwed down on the external Interrupter 
Relay connections. 

 

Turn on the AC power to the rectifier and confirm the 

Blue Heartbeat LED 

on the Hero board 

is blinking once per second (this can take up to ten minutes) 

 

The external Interrupter Relay must be wired correctly and operational before installation 
of the Tap Commander.

 

o

 

Hero 1 

 Test the Interrupter Relay by issuing a Rectifier Off command from 

Omniview. Confirm the relay is open by using a multimeter to measure mV across 
the shunt, the mV reading should be zero. After confirmation, issue a Rectifier On 
command from Omniview.

 

o

 

Hero 2

 - 

Test the relay by pressing and holding the red “Interrupter Relay” button 

for three seconds, on the Hero 2 Interface Board. The 

Red LED 

should illuminate 

below the red “Interrupter Relay” button signifying the relay is open. Confirm the 

relay is open by using a multimeter to measure mV across the shunt, the mV reading 

should be zero. After confirmation, press and hold the red “Interrupter Relay” 

button until the 

Red LED 

goes out on the Interface Board. 

NOTE: The button on the 

Interface Board are only active when the blue Heartbeat light is flashing.

 

 

The external Interrupter Relay is an integral part of the Tap Commander design. If the 
external Interrupter Relay is not working correctly, 

do not 

proceed with installation of the 

Tap Commander until that problem is resolved 

3.

 

Installation: 

 

Power down the AC to the Rectifier 

 

Remove the shorting bars from the rectifier  