Maintenance
CIRCUIT BOARD TEST:
A standard 110V Neon circuit tester can be used for testing.
CHECKING FUSE:
With the power OFF, disconnect red wire from Terminal 1 and
secure it out of the way without touching any metal. With power
ON, test across Terminals 3 and 4. If tester does not light, replace
fuse.
CHECKING HOT ROD:
With the power OFF, disconnect red wire from Terminal 1 and secure it out of the way without touching any
metal. With power ON, test between Terminal 1 and end of disconnected wire. If tester does not light, replace
the hot rod.
Installation and Operation
INSTALLING COMPLETE AXLE ASSEMBLY
To install the axle assembly (1), simply position the
assembly at the rear of the machine (2) with the
removable end cap (3) on the left side as pictured above.
Insert two bolts (4) on each side through the machine
base (2) and bearing block plates (5), slide on washers
and fasten washers with hex nuts (6).
REPLACING THE INDIVIDUAL AXLE
To replace the axle, remove cap from end of one bolt (7)
and unscrew wing nut (8), then pull screw from bearing
block (9) and open to release the axle assembly, replace
axle assembly with removable cap as shown above.
LOADING AND ADJUSTING AXLE FOR DIFFERENT
WIDTH FILMS
Loosen the wing nuts and swing out upper bearing blocks
on both sides.
Lift out the axle assembly, unscrew the movable end cap
and position fixed cap for film size being used and secure with pin and o-ring (10).
Place the core of the film against the fixed cap and feed film from bottom of roll (check threading diagrams
on previous page). Replace the movable end cap and screw tightly into film core. Replace the axle back into
bearing blocks and then tighten wing nuts to desired film tension.