8
Installation
UNPACKING
1. Remove the strips from the packaging (Fig. n°10) and lift (h) the cardboard box. The machine is fixed with
two plates to the pallet.
POSITIONING
Position the pallet, with the dough mixer, on a flat surface and unscrew (a) the screws that fix the machine to
the pallet (Fig. n°12). At this point, with care, turn the machine over onto one side and unscrew the screws to
remove the anchoring plates (b). Fixed the screws removed onto the bottom cover. Position the dough mixer in
the predestined place. The surface on which the dough mixer is to be positioned must take into consideration
the dimensions indicated in Tab. 1 (based on the model) therefore the support surfaces must be wide enough
to contain it (Fig. n°13) and must be well levelled and dry away from water and heat sources with suitable
ventilation and lighting in relation to the space necessary for its use and safe keeping. (The machine must
also be positioned in a non saline room with a maximum humidity of 75% and a temperature included between
+5°C and +35°C; however in rooms that can not cause malfunctioning of the machine).
ELECTRIC CONNECTION
Check that the data reported on the technical plate-serial number (Fig. n°15), on the dispatch note and in the
order carried out correspond; If this is not the case, immediately contact the manufacturer for an explanation.
Make sure at this point that the plant is up to standards and that the cable and the earth plant function
perfectly.
The dough mixer is equipped with a UL listing power supply cord and a plug. Connect the dough mixer with a
120 V. / 230V. - 60 Herz electric circuit. Moreover check that features on the rating plate - serial number (FIG.
n°15) correspond to the features shown in the consignment and delivery note.
PRELIMINARY CHECKS
Before testing make sure that the protection located on the tank is lowered up to slightly touching the bowl,
after which test functioning as follows:
• Activate the “START” button and the “STOP” button (Fig. n°18);
• Check that when lifting the protection the machine stops functioning;
• With the machine on, remove the plug and reinsert it to check if the machine does not automatically restart;
• In the liftable head and removable bowl versions, check if the machine stops running when the head is
unlatched (Fig. No. 19);
• TIMER optional;
• For double speed models select speeds 1 or 2 by rotating the selector switch and pressing the “START”
button; press the “START” button each time the speed is changed.
In models with a liftable head, make sure that the head and guard are completely lowered before testing the
machine. The head must be horizontal and the locking knob must be pointed down (Fig. No. 20). Also verify
that the bowl is correctly inserted and locked by the disc. After these operations have been completed, it is
possible to begin the functional verification as described above.
Содержание MX-IT-0020-F
Страница 19: ...19 Instructions Fran ais mat riaux utilis s pour les diff rents composants voir chap 4 par 4 1 Figure Drawings...
Страница 20: ...20 Figure Drawings...
Страница 21: ...21 Figure Drawings...
Страница 22: ...22 Figure Drawings...
Страница 23: ...23 Figure Drawings...
Страница 24: ...24 Figure Drawings...
Страница 25: ...25 Parts Breakdown Model MX IT 0020 F 45417 Model MX IT 0020 FT 47417...
Страница 28: ...28 Model MX IT 0030 F 45418 Model MX IT 0030 FT 47418 Parts Breakdown...
Страница 31: ...31 Parts Breakdown Model MX IT 0020 R 47087 Model MX IT 0020 RT 47287...
Страница 35: ...35 Model MX IT 0030 R 47088 Model MX IT 0030 RT 47288 Parts Breakdown...