background image

RIGHT

WRONG

Flow

Side elevation

When installed horizontally the ribs must be at the bottom to 

ensure correct operation. 

2.1 Condensate Drain installation

1.

Unit comes complete with external drain pipe (21.5mm waste

pipe). Use conventional plumbing connections to link up with

U-trap or alternative drain method (Solvent cement

connections or compression fit connections are

recommended). The condensate must be discharged under a

water level in a U-trap drainpipe or an alternative drain

method which acts as an airlock.

2. This condensate discharge connection is suitable for 21.5mm

dia. overflow pipe. Solvent cement should be used to make

the joint.

3. If using a U-trap please ensure the U-trap has been filled to

a suitable level of water to avoid any air locks.

4. If the condensation pipe is fitted in an unheated space the

pipe should be in insulated to prevent freezing.

Nuaire recommend MVHR-DRAIN be used as the primary

condensate take-off. (see figures 4a and 4b).

Fixing

Offer up the MVHR-DRAIN inlet to the threaded tail of the 

appliance waste outlet or MVHR-DRAIN knuckle or running

adaptor, and tighten the threaded cap sufficiently hand-tight to

provide a water-tight seal (check that the cap screws on square

and does not ‘cross-thread’). When the screwed cap is tight, the

MVHR-DRAIN

body is secure.

1.

Cut the pipe to length, allowing for the full compression

socket depth (using an appropriate pipe cutter, such as a

Hepworth rachet pipe cutter).

2. Remove any ‘swarf’ from the end of the plastic pipe.

Ream the copper pipe end to remove any ‘burr’, and file if

necessary to remove any external sharp edges. Mark the

socket depth on the pipe, and check that the pipe section to

be jointed is free of any surface damage which may affect

the joint seal.

3. Unscrew the cap from the MVHR-DRAIN outlet, and slide the

cap and rubber seal onto the pipe.

4. Insert the pipe end fully into the socket.

5. Slide the rubber seal and screwed cap up against the face of

the socket, and tighten the cap sufficiently hand-tight (check

that the cap is square to the body and does not ‘cross-

thread’). Hand tight should be adequate to form a proper seal.

2.2 Extract/input areas

The unit is designed to extract air from all wet rooms 

e.g. bathroom, kitchen, en-suite, utility room (with sink).

WC’s do not need to be ventilated if openable windows are fitted.

Supply air should be to all habitable rooms e.g. bedrooms and

lounge. Extract / input grilles should be adjustable valve types

(not supplied).

External grilles to have a minimum free area of 12,250 sq mm.

2.3 Ducting

Before commencing ducting installation reference should be

made to building regulations document “Domestic ventilation

compliance guide”. This document supports ADF2010 and

details installation, testing and commissioning of all ventilation

systems.

It is recommended that rigid ducting must be used it all times. 

Flexible ducting has a very high resistance and it is impossible

to calculate how much resistance will be on a system if used.

If used the flexible ducting must be kept to a minimum and

should always be pulled taut. A maximum of 300mm should 

be used on each leg.

To prevent condensation on the outside of the outside air inlet

duct and the air outlet duct from the MRXBOX95B-LP1, these

ducts should be insulated. 

Ducting must be installed in such a way that resistance to 

airflow is minimised. Bends should be kept to a minimum.

A minimum distance of 300mm between the appliance and 

any bends in ductwork is recommended.

204 x 60mm rectangular ducting should be used. (Refer to

dwelling ducting design drawing, figure 6 on page 4 for further 

information).

Ducting joints must be sealed with silicone type sealant and

needs to be taped. Ducting shall be adequately and reliably

fixed to the appliance.

2

27. 11. 17. Leaflet Number 671582

Installation and Maintenance

MRXBOX95B-LP1 Mechanical Ventilation with Heat Recovery & Summer Bypass

Figure 4a. MVHR-DRAIN condensate drain, running to SVP.

(shown on a standard unit).

Figure 4b. MVHR-DRAIN correct installation.

Figure 2. Installing the unit using appropriate fixing bolts.

(shown on a standard unit).

204 x 60mm 

ducting in 

ceiling void.

Side view of unit 

mounted in the ceiling void.

Air valve 

in ceiling.

Figure 3. Typical side view example of a (Standard unit) mounted in

a ceiling void using 204 x 60mm rectangular ducting and air

valves.

Steel mounting bracket

Содержание Ecosmart MRXBOX95B-LP1

Страница 1: ...Voltage Frequency and Phase complies with the rating label Please note a clear working space is required around the installed unit to allow the cover to be removed and provide sufficient access for ma...

Страница 2: ...ad Hand tight should be adequate to form a proper seal 2 2 Extract input areas The unit is designed to extract air from all wet rooms e g bathroom kitchen en suite utility room with sink WC s do not n...

Страница 3: ...step 2 calculation Step 3 The required airflow rates are as follows n the maximum whole dwelling extract ventilation rate e g boost should be at least the greater of step 1 and step 2 Note that the ma...

Страница 4: ...oom to outside via air brick Supply and extract ducts from external air bricks to the unit needs to be insulated Minimum distance as specified in Building Regulations Top of ceiling void Intake air fr...

Страница 5: ...ir Spigot 4 Air Exhaust Spigot 1 Air 250 Intake Heat exchanger Bypass chamber Supply fan Extract fan 21 5mm condensate pipe Drip tray Wire frame lter Wire frame lter Bypass 4 damper 1 2 3 735 Filter a...

Страница 6: ...al cable tray as other cables Figure 9 7 0 Electrical Connection Please note the electrical connection of the unit must be be carried out by a qualified electrician The unit is supplied with a flexibl...

Страница 7: ...al gov uk building regulations approved documents partf associated A calibrated moving vane anemometer and hood will be required to carry out commissioning 5 Adjustment valves should be locked in plac...

Страница 8: ...ty is conditional on planned maintenance being undertaken This warranty is void if the equipment is modified without authorisation is incorrectly applied misused disassembled or not installed commissi...

Отзывы: