Installation and Maintenance

AXUS AXR High Temperature Axial Fans

4

08. 05. 17. Leaflet Number 671063

Electrical Installation - Motors

Motors comply with BS5000 and IRC34-1; they have sealed for

life ball bearings, IP55 enclosures and class H insulation.

Motors are tested for high temperature operation in accordance

with BS7346 (Part 2) and PR EN 12101-3.

NB Please note the requirements for maintenance of the motor.

Failure to comply with the recommendations will invalidate 

any warranty claim.  

Wiring General

Electrical supply wiring connection is to an externally mounted 

terminal box on the case exterior. The box is pre-wired to the

motor with heat resisting cable. 

NOTE: We recommend D.O.L. starting whenever possible. 

Units of 4kW and above have provision for Star/Delta starting

if this is required (and is permitted by the relevant authorities). 

Two speed motors must be wired for D.O.L. starting only.

Two speed motors, allowing normal ventilation at reduced 

noise levels, are available on all units.

Connection details

Fans with motors up to 3.0kW are suitable for connection in

the STAR method and also to a Direct On Line (DOL) starter.

The Star connection will be made at works on all but the EEXD

motors..

Fans with motors of 4.0kW and above will have all six ends of

the motor windings brought out to the terminal box on all but

the EEXD motors. These motors should be connected in the

DELTA mesh for connection to a DOL starter.

4.0kW motors and above are also suitable for connection to a

STAR / DELTA controller, but as smoke fans are required to

start with the minimum of delay in an emergency, this method

of control is not recommended.

Motor overload protection should be provided for continuous

running and routine testing. This protection must be defeated

for emergency operation to allow the fan to run to destruction.

Supply fuses should be H.R.C. type.

Start up procedure

Ensure that the impeller rotation follows the label arrow 

indicator on the casing. Should the direction be incorrect on

three phase units, reverse any two of the supply leads. Care

should be taken to set correct rotation as incorrect rotation

may result in damage to the motor. 

Equipment should be run for approx. 30 minutes to ensure 

correct operation. 

If any fault occurs, the equipment  should be switched off.  

Do not re-start until the fault has been rectified.

This equipment incorporates rotating and moving parts as 

well as electrical components and conductors. 

It is the responsibility of the installer to ensure that any such 

items that remain externally accessible once the 

equipment is installed are adequately guarded.

Содержание AXUS AXR

Страница 1: ...ames In addition to making the fans easier to handle during transit the frames also afford protection for the motor section We advise that the wooden frames should remain on the fans until the moment of actual installation and fixing Handling the unit is best carried out wth the unit fixed to the transit frame When lifting use spreader beams through the transit frame ensuring the unit is evenly ba...

Страница 2: ...t Number 671063 Danger This equipment incorporates rotating and moving parts as well as electrical components and conductors It is the responsibility of the installer to ensure that any such items that remain externally accessible once the equipment is installed are adequately guarded This precaution is necessary to avoid the possibility of accidental injury or death Particular attention must be p...

Страница 3: ...den cappings set to the maximum overhang position of 15mm The roof flashing can be run up the sides of the curb to finish just beneath the top Alternatively if adequate clearance is available the flashing could be run over the top of the capping prior to lowering the unit onto the curb When installed the curb must be bolted securely to the roof trimmer angles Soaker sheet Soaker sheets are manufac...

Страница 4: ...tors Fans with motors of 4 0kW and above will have all six ends of the motor windings brought out to the terminal box on all but the EEXD motors These motors should be connected in the DELTA mesh for connection to a DOL starter 4 0kW motors and above are also suitable for connection to a STAR DELTA controller but as smoke fans are required to start with the minimum of delay in an emergency this me...

Страница 5: ... on a three phase unit simply reverse any two of the supply connections in the isolator box Wiring Diagrams S L1 L2 L3 Single Speed 3 phase below 4kW 400V 3 phase 50Hz supply Fan unit L 4 1U 1V 1W L U1 L V1 L W1 L U1 W2 L V1 U2 L W1 V2 L W V U 4 Notes T S L N S L2 N L1 L L N L2 N N L1 L L L3 N N L2 U V W THREE PHASE UNITS For specialist connections not shown always refer to the wiring diagram supp...

Страница 6: ...ordance with the details contained in this manual and general good practice Specific Commissioning and Service Requirements Motors for Smoke Extract Fans These motors are used to provide a SAFETY FUNCTION for people in the event of fire in public premises they are therefore subject to strict constraints concerning their operating and maintenance Operating Constraints i Check on the nameplate that ...

Страница 7: ... general requirements should be noted 5 1 Where access to any part of equipment which moves or can become electrically live are not prevented by the equipment panels or by fixed installation detail eg ducting then guarding to the appropriate standard must be fitted 5 2 The electrical installation of the equipment must comply with the requirements of the relevant local electrical safety regulations...