2.5 Air permeability and 
infiltration

Is the uncontrolled exchange of air between inside and outside

through cracks, porosity and other unintentional openings in

the building. ADF2006 gives an allowance for this in both 

multi and single storey buildings, however ADF2010 has an

allowance for multi storey only. Additionally ADF2010 only

applies this allowance for dwellings leakier than 5 m

3

/(h.m

2

) at

50Pa. (See below).

2.6 ADF 2006 Ventilation 
calculations
Continuous supply and extract

Step 1: 

Determine the whole building ventilation rate 

from Table

2.

Allow for infiltration by subtracting from this value:

for multi-storey dwellings: 0.04 x gross internal volume of 

the dwelling heated space (m

3

);

for single-storey dwellings: 0.06 x gross internal volume of 

the dwelling heated space (m

3

).

Step 2: 

Calculate the whole dwelling air extract rate at 

maximum operation by summing the individual room rates for

‘minimum high rate’ 

from Table 1.

(For sanitary accommmodation only, as an alternative, the

purge ventilation provisions given in ADF 2006 can be used

where security is not an issue. In this case ‘minimum high

extract rate’ for the sanitary accommodation should be omitted

from the step 2 calculation).

Step 3: 

The required airflow rates are as follows:

the maximum extract rate (e.g. boost) should be at least 

the greater of step 1 and step 2. Note that the maximum 

individual room extract rate should be at least those given 

in table 1

. for minimum high rate.

the minimum air supply rate should be at least the whole 

building ventilation rate found in step 1.

2.7 ADF 2010 Ventilation 
calculations
Design of MVHR systems

The MVHR system has been sized for the winter period.

Additional ventilation may be required during the warmer

months and it has been assumed that the provisions for purge

ventilation (e.g. openable windows) could be used.

Step 1:

For any design air permeability, determine the whole

dwelling ventilation supply rate 

from Table 2.

As an alternative where the design air permeability is intended

to be leakier than (>) 5m

3

/(h.m

2

) 50 Pa, allow for infiltration

for all dwelling types by subtracting from the whole dwelling

ventilation supply rate 

from Table 2

; 0.04 x gross internal 

volume of the dwelling heated space (m

3

).

Step 2:

Calculate the whole dwelling extract ventilation rate by

summing the individual room rates for ‘minimum high rate’ 

from

Table 1.

(For sanitary accommodation only, as an alternative, the purge

ventilation provisions given in ADF 2010 can be used where

security is not an issue. In this case ‘minimum high extract rate’

for the sanitary accommodation should be omitted from the

step 2 calculation).

Step 3: 

The required airflow rates are as follows:

the maximum whole dwelling extract ventilation rate 

(e.g. boost) should be at least the greater of step 1 and 

step 2. 

Note that the maximum individual room extract rate should 

be at least those given

in table 1.

for minimum high rate.

the minimum air supply rate should be at least the whole 

building ventilation rate found in step 1.

For Scotland refer to BRE Digest 398.

3

Leaflet Number 671597 January 2013

Installation and Maintenance

XBOXER-MICRO Mechanical Ventilation with Heat Recovery & Summer Bypass

Any air intake terminal MUST be installed in accordance with the

appropriate regulation. 

As a guide, the BS5440 series of British Standards deals with

this issue and currently states that an air intake must be at a

minimum distance of 300mm from a gas boiler balanced flue.

Installers are advised to be aware of the requirements of this

standard when installing ‘through the wall’ supply air ducting.

Similarly, supply and extract air grilles should be at least

300mm apart.

Содержание XBOXER-MICRO

Страница 1: ...e outside air reaches 200C when the outer air temperature returns below this level the unit returns to its original state Outside air supplied through the bypass is still being filtered so the air qua...

Страница 2: ...les to have a minimum free area of 12 250 sq mm 2 3 Ducting Before commencing ducting installation reference should be made to building regulations document Domestic ventilation compliance guide This...

Страница 3: ...months and it has been assumed that the provisions for purge ventilation e g openable windows could be used Step 1 For any design air permeability determine the whole dwelling ventilation supply rate...

Страница 4: ...nsate pipe 457 250 502 83 155 106 81 122 99 122 150 122 257 1 3 2 4 1 3 2 4 1 3 2 4 4 1 3 0 Dimensions mm Figure 5 Also shows the working space required 4 0 Ducting arrangements Fig 6 Typical ducted a...

Страница 5: ...ion of 3mm 1 2 Customer wiring Figure 8 For good EMC engineering practice any sensor cables or switched live cables should not be placed within 50mm of other cables or on the same metal cable tray as...

Страница 6: ...it should not be adjusted as it will have a detrimental effect on the indoor air quality and could result in condensation and mould growth The label covering the control has an adhesive panel which sh...

Страница 7: ...r use with this product 6 0 COMMISSIONING REQUIREMENTS 6 1 General pre commissioning checks relevant to safe operation consist of the following Ensure that no foreign bodies are present within the fan...

Страница 8: ...8 Leaflet Number 671597 January 2013 Western Industrial Estate Caerphilly United Kingdom CF83 1NA T 029 2085 8200 F 029 2085 8300 E ahu nuaire co uk W www nuaire co uk...

Отзывы: