Page No 18 of 52 Reznor, RHC21 8000 Installation EN May 2021 D301319 Issue 0

Single wall seamless aluminium or stainless 
steel flue pipes are required. All joints must be 
sealed to prevent the products of combustion 
from leaking into the building. If the flue 
passes through a combustible element of the 
building it must be enclosed by a sleeve of non-
combustible material and separated from the 
sleeve by a minimum of 25 mm air break. The 
temperature of any combustible material near 
to the flue must not exceed 65°C when the 
heater is in operation. The flue must be at least 
150 mm away from any combustible material.
Single wall flue pipe exposed to cold air or run 
through unheated areas should be insulated. 
Where condensation is unavoidable, provision 
must be made for the condensation to flow 
freely to a point to which it can be released, 
i.e. a drain or gully. The condensation drain 
from the flue must be constructed from non-
corrodible material not less than 20 mm 
diameter. Copper or copper based alloys must 
not be used for condensation drains.
Vertical flue runs greater than 3m long will 
require a condensate drain fitting between the 
flue outlet of the heater and the vertical flue 
pipe. Alternatively, insulated flue pipe should be 
considered. 
Horizontal flue runs should be installed with a 
slight gradient of approximately 5° towards the 
terminal. 
Due consideration should be given to the 
possibility of condensation from the flue 
freezing on any footpaths that pass below the 
terminal.

4.10 Gas supply

Attention : gas service connection Rc 3/4 for 
models RHC21 8000 & Rc 11/4 for models 
RHC21 8000M.
RHC21 8000 air heaters are designed to operate 
on natural gas (G20 / G25 / G25.3). Refer to the 
specifications in section 2 of this document and 
to the data plate for details of supply pressures.
A competent and/or qualified engineer is 
required to either install a new gas meter to the 
service pipe or to check that the existing meter 

is adequate to deal with the rate of gas supply 
required. Installation pipes should be fitted in 
accordance with national standards so that the 
supply pressure, as stated in the technical data 
section will be achieved.

It is the responsibility of the competent engineer 
to ensure that other relevant standards and 
codes of practice are complied with in the 
country of installation. Pipes of smaller size 
than the heater inlet gas connection must not 
be used. The complete installation must be 
tested for soundness as described in the country 
of installation. Support gas piping with pipe 
hangers, metal strapping, or other suitable 
material. 

Do not rely on the heater to 
support the gas pipework 
installation.

Before installation, check that 
the local distribution conditions, 
nature of gas and pressure, and 
adjustment of the appliance are 
compatible.

This appliance is designed for a 
maximum gas supply pressure of 
50mbar. When pressure testing the 
supply piping with test pressures 
above 50mbar, disconnect the 
heater and manual valve from the 
gas supply line that is to be tested. 
Cap or plug the supply line.

To facilitate servicing, the air heater must be 
fitted with an approved gas service tap and 
union fitting or union tap adjacent to the 
appliance.
The inlet gas supply line must be installed so as 
to permit the access door to be opened and to 
allow removal of slide out burner assembly.
Check that the gas category is in accordance 
with the data described on the air heater.
An adequate gas supply sized to provide the 
dynamic pressure for the volume required for 
the air heater(s) is essential to maintain the 
nominal heat input.

Содержание Reznor RHC21 8000

Страница 1: ...out by appropriately qualified persons The manufacturer does not take any responsibility in the event of non observance of the regulations concerning the connection of the apparatus causing a dangero...

Страница 2: ...rn the air heater OFF for short periods 28 5 13 To turn the air heater OFF for long periods 28 6 Servicing and maintenance 30 RHC21 8125M15 8150M18 8125M21 and 8200M24 component layout 30 RHC 8045 09...

Страница 3: ......

Страница 4: ...ld not be used for closing down the main burner as it switches off the fan prematurely and may damage the heat exchanger invalidating the warranty Important notice to installers Before installation ca...

Страница 5: ...igned for use in hazardous atmospheres containing flammable vapours or combustible dust in atmospheres containing chlorinated or halogenated hydrocarbons or in appliances with airborne silicone substa...

Страница 6: ...of installation or the country codes and gas categories as shown in this instruction manual it will be necessary to contact the distributor or manufacturer to provide the necessary information for the...

Страница 7: ...scribed dimensions see table 8 The inlet temperature measured at the heat exchanger inlet is lower than the value stated on the chart see fig 5 dew point occurrence chart 1 3 Definitions Module The ga...

Страница 8: ...3 m h 6 07 8 08 9 91 13 00 16 63 19 83 22 43 26 00 Gas Consumption Low Fire Hs G25 3 3 m h 1 82 2 43 2 66 4 01 4 67 5 32 6 67 8 56 Gas Service Connection Inches BSP 3 4 3 4 3 4 3 4 11 4 11 4 11 4 11 4...

Страница 9: ...e G20 kg h 44 57 57 47 76 73 93 59 123 18 152 24 164 10 189 49 Mass Flow Rate Flue Gases High Fire G25 kg h 48 66 58 64 74 90 97 44 125 65 143 83 161 37 190 96 Mass Flow Rate Flue Gases High Fire G25...

Страница 10: ...ion RHC21 8045 09 8060 12 8075 09 8100 12 8125M15 8150M18 8175M21 8200M24 A 741 950 741 950 1272 1482 1691 1900 A1 200 239 200 239 210 210 190 229 A2 541 711 541 711 1062 1272 1501 1671 B 400 400 400...

Страница 11: ...12 8125M15 8150M18 8175M21 8200M24 F 350 350 350 350 350 350 350 350 F1 175 175 175 N A 175 175 175 N A G 25 25 25 25 25 25 25 25 H 1244 1244 1844 1844 1844 1844 1844 1844 J 432 401 432 385 370 363 3...

Страница 12: ...ure 3 Front View Figure 3 1 RHC21 8045 09 8060 12 8075 15 8100 12 Figure 3 2 RHC21 8125M15 8150M18 8175M21 8200M24 RHC21 8045 09 8060 12 8075 09 8100 12 8125M15 8150M18 8175M21 8200M24 A 741 950 741 9...

Страница 13: ...ry Check the shipping label and data plate to ensure the specification of gas and electrical supplies are compatible Read this document and become familiar with the installation requirements and the a...

Страница 14: ...RO C 4000 R JL EURO C 4000 D JL CONDENSATION POINT 20 C 0 C 20 C 40K 20K 0K T T INLET AIR TEMPERATURE 30K CONDENSATION ZONE AT THE HEAT EXCHANGER 10K TEMPERATURE RISE OVER THE HEAT EXCHANGER Figure 5...

Страница 15: ...ction of the appropriate heat input 4 6 Compartment dimensions RHC21 H H1 Y Y2 W W1 E 8045 09 741 701 1244 1170 400 400 450 8060 12 950 910 1244 1700 400 400 450 8075 09 741 701 1844 1770 400 400 450...

Страница 16: ...on instructions for making joints including connections to the air heater for passing through a building element and for support requirements Gasket sealed single wall seamless aluminium or stainless...

Страница 17: ...ould be insulated Where condensation is unavoidable provision must be made for the condensation to flow freely to a point to which it can be released i e a drain or gully The condensation drain from t...

Страница 18: ...er to the specifications in section 2 of this document and to the data plate for details of supply pressures A competent and or qualified engineer is required to either install a new gas meter to the...

Страница 19: ...appliance wiring diagram is supplied as a separate document A constant 230 volt 50 Hertz single phase with neutral link fused electricity supply is required All heaters and controls must be earthed A...

Страница 20: ...llow instructions supplied with such panels Thermostat s and or temperature sensor s should be mounted on a vibration free surface Room thermostat s sensor s should be mounted about 1 5m above floor l...

Страница 21: ...rect voltage The same result should be obtained by connecting the test leads between live and neutral Connect the voltmeter test leads to N and E A reading of 0V should be obtained If these tests do n...

Страница 22: ...ecessary due to air still being present in the gas pipe Should the air heater still not light refer to Fault Finding section 8 The gas pressure must correspond to the data in table 3 on page 9 If the...

Страница 23: ...tate clockwise to increase pressure CO2 Refit cap after adjustment 1 Offset adjustment 2 Inlet pressure measuring point 3 CO2 adjustment point throttle 4 Offset pressure measuring point Figure 8 Gas v...

Страница 24: ...Fire Throttle G25 3 8 60 8 60 8 60 8 60 8 60 8 60 8 60 8 60 CO G25 3 ppm 50 ppm Throttle Turns from G20 Top Burner N A N A N A N A 2 0 out 2 0 out 2 25 out 5 5 in Throttle Turns from G20 Single Bottom...

Страница 25: ...n the master burner following the commissioning procedure given overleaf Once the master burner has been commissioned the slave burner must be commissioned To commission the slave burner the master bu...

Страница 26: ...ttle a set number of turns as indicated in the combustion data table If the chamber insulation has been replaced the organic binders will burn off during the first few minutes of operation This will r...

Страница 27: ...the burner will run at the ignition speed for a few seconds to allow the flame to stabilise Following flame stabilisation the fan speed will increase to high fire to allow the heat exchanger to warm u...

Страница 28: ...rn the air heater OFF for long periods Adjust the room thermostat to OFF or its lowest setting When the fan has stopped turn OFF the gas supply and then switch OFF the electricity supply to the air he...

Страница 29: ...ior to activation of the ignition device Safety time The safety time is the delay between the gas valve being energised and the flame sensor checking for the presence of a flame This is a period of 4...

Страница 30: ...1 x 8175 dependant on unit model 10 Tapitscrew 2 Gas train assembly 11 Washer 3 Limit stat bracket 12 Outlet collar AS D 130 VRA 4 Limit stat clips 13 Tube stainless steel 304 5 Limit control LC3 14...

Страница 31: ...EN May 2021 D301319 Issue 0 Page No 31 of 52 Ref Description 19 U shape silicon gasket 20 Silicon gasket 21 Control box 1 bracket 22 Control box 2 bracket 23 Double control box assembly with controlle...

Страница 32: ...bly 10 Limit control LC3 2 Tapitscrew 4 8 x 13 11 Clips 3 U shape silicon gasket 12 Limit stat bracket 4 Silicon gasket 13 Stainless steel 304 spigot 5 Gas train bracket 14 Stainless steel 304 90 elbo...

Страница 33: ...servicing is recommended When any service is completed be sure that components are reassembled correctly to ensure that no unsafe condition exists Upon completion of the service carry out the commissi...

Страница 34: ...unit RHC21 8045 09 8060 12 8075 09 8125M15 2 off 8150M18 2 off and 8175M21 1 off gas valve flange assembly 5 The gas valve can now be disconnected from the venturi by removing the fixing screws There...

Страница 35: ...it gas valve in reverse order ensuring the o ring is fitted between the gas valve and venturi 8 Follow start up and commissioning procedures 7 2 Venturi cleaning and replacement 1 Clean the venturi in...

Страница 36: ...es combustion fan 6 Refit remaining items in reverse order 7 Follow start up and commissioning procedure 7 3 Combustion fan cleaning and replacement 1 Follow steps 1 to 4 from gas valve replacement an...

Страница 37: ...air drying air should not exceed 1 5 bar 8 Replace the burner gasket if necessary 9 Refit in reverse order 10 Follow start up and commissioning procedure 7 5 Burner chamber tube insulation check and...

Страница 38: ...The first is located at the front of the chamber where the tubes are secured The second is located on the lower right side of the chamber where the probes are normally located It is recommended that b...

Страница 39: ...ket to release the probe mounting bracket 4 Pull probe mounting bracket away from the burner chamber to extract the burner probes 5 The burner probe assembly can now be removed from the heater 6 Revie...

Страница 40: ...1 Refit all parts in reverse order 12 Follow start up and commissioning procedure 7 7 Replacement of LC3 safety thermostats 1 Disconnect LC3 electrical connectors 2 Remove LC3 protective cap and lock...

Страница 41: ...ontroller 3 Remove program key and refit into new controller 4 Fix new controller to electrical panel and reattach all wiring 5 Follow start up and commissioning procedure 7 9 Replacement of ignition...

Страница 42: ...ct see technical data table 4 Integrity of supply circuit Does the lockout light illuminate Does the lockout light go off after pressing switch for 3 seconds CHECK 1 LED status light flash codes 2 LC3...

Страница 43: ...at demand still present 2 Gas supply purged 3 Supply pressure 4 Throttle positioning see commissioning data table 5 Flame sensor probe corroded 6 Flame signal min 1 0 A 7 Flame sensor probe bent 8 Int...

Страница 44: ...d 03 25327 01 All Lockout Reset Switch 60 61998 All Gas valve lead 1030864 All Gas Valve 03 25800 8045 09 8060 12 8125M15 6 Gas Valve 03 25801 8075 09 8125M15 9 8150M18 8175M21 9 Gas Valve 1030499 810...

Страница 45: ...eater MUST NOT be controlled by switching the main electrical supply to it ON and OFF The ignition sequence will commence each time the external controls e g Time clock room thermostat etc call for he...

Страница 46: ...urposes and the air supply to the heater must not be restricted in any way Combustible materials must not be stored adjacent to the heater If at any time a gas leak is suspected turn OFF the gas suppl...

Страница 47: ...1 93 6 8075 09 75 8 21 8 0 177 0 022 0 001 82 8 88 7 0 0 0 0 52 97 3 85 3 91 9 8060 12 61 3 19 8 0 106 0 018 0 001 82 2 88 3 0 0 0 0 54 97 1 84 6 91 2 8045 09 45 7 14 7 0 111 0 017 0 001 81 6 87 8 0...

Страница 48: ...1 85 4 93 5 8075 09 76 6 21 7 0 177 0 022 0 001 83 7 88 4 0 0 0 0 69 97 3 85 2 93 0 8060 12 61 3 19 7 0 106 0 018 0 001 82 1 88 1 0 0 0 0 68 97 1 84 4 91 2 8045 09 45 5 14 8 0 111 0 017 0 001 81 2 87...

Страница 49: ...7 1 85 2 93 3 8075 09 76 0 21 7 0 177 0 022 0 001 83 1 88 4 0 0 0 0 70 97 3 85 1 92 2 8060 12 61 3 19 8 0 106 0 018 0 001 82 2 88 3 0 0 0 0 66 97 1 84 6 91 2 8045 09 45 8 14 8 0 111 0 017 0 001 81 7 8...

Страница 50: ...e Address Site name Commissioning Engineer Name Gas Safe Reg No Company Name Commissioning Date Burner Fuel type Inlet Pressure mbar Working Pressure mbar Burner Pressure Low Fire mbar High Fire mbar...

Страница 51: ...Reznor RHC21 8000 Installation EN May 2021 D301319 Issue 0 Page No 51 of 52 Notes...

Страница 52: ...9707 reznorsales nortek com www reznor eu Nortek Global HVAC is a registered trademark of Nortek Global HVAC limited Because of the continuous product innovation Nortek Global HVAC reserves the right...

Отзывы: