Filling and venting the system
Buffer vent
➢
Fill the central heating side though the filling loop in the VVM320
➢
Vent the hot water coil via the coil vent
➢
Vent the buffer via the buffer vent
➢
Vent all high points on pipework
➢
Pressurise the system to the required cold fill pressure (typically 1-1.5 bar).
➢
The hot water cylinder must be filled prior to turn on.
➢
The cylinder is filled via the cold-water supply as any standard cylinder.
➢
Ensure under floor heating/radiators are filled and vented correctly.
➢
There should be no gurgling sounds from the system.
Coil vent
NB. The Outdoor Unit Must be powered up a minimum of 6 hours before the indoor unit.