PROJECT MANAGEMENT  /  Preparation Checklist

ENSURE YOU TICK THE SPECIFIC BOXES THAT APPLY AS YOU PROGRESS

2 Sided Shower: Ensure the floor is level and the walls are plumb and flat.

Position all framing for solid fixing for the shower tray, shower and plumbing fittings 

(refer to the specific tray, liner and shower instruction manual at www.newline.co.nz).

Ensure all plumbing items have been installed prior to the lining being attached.

Alcove Shower: Critical that the walls are constructed plumb and flat within the 

specifications of the specific shower being installed.

ACRYLIC TRAY AND LINER OPTION
•  Detailed installation instructions are packed with the shower tray for tray and lining 

installation. 

•  Alcove application may require specific detailing of framing or plasterboard lining. This 

will need to be competed prior to framing.

•  Shower waste and supply fittings must be installed by a registered plumber.

TILE INSTALLATION OPTION WITH STANDARD PROFINISH

TM

 TILE TRAY 

•  The “ProFinish

TM

 Tile Tray” must be installed as per the ProFinish

TM

 installation 

instructions with the packaged product.

•  The leak proof waste and supply fittings must be installed by registered plumber.
•  Waterproofing must be undertaken by certified applicator and a Producer Statement 

provided. There is a list of 14 proven systems listed in the back of these instructions.

•  Tiling: 

1. 

Manufacturers waterproofing cure times must be adhered to.

2. 

The notched trowel lines for the tile mortar must be all leading to the waste outlet.

3. 

Ensure tiles are laid according to the falls in the tray. 

4. 

The boundary line where the shower screen sits must be level.

5. 

Tile adhesive cure times must be allowed before commencing shower installation.

Содержание Raymor RAY1200CHR

Страница 1: ...PRODUCT CODES RAY1200CHR RAY1200WHT INSTRUCTION MANUAL VERSION 16 0001 Newline Group Limited Freephone 0508 639 5463 www newline co nz SLIDING DOOR SET INSTRUCTION MANUAL...

Страница 2: ...INSTRUCTIONS BEFORE INSTALLATION AND USE CONTENTS PAGE Important Information 1 Preparation Checklist 2 Supplied Components 3 Layout Procedure 5 Installation Steps 6 Newline Group Limited Freephone 05...

Страница 3: ...ill chip and destroy the glass panel Installation Glass panels and assemblies are heavy Two man lifting is recommended for handling and installation Determine positioning of wiring and piping within w...

Страница 4: ...specific detailing of framing or plasterboard lining This will need to be competed prior to framing Shower waste and supply fittings must be installed by a registered plumber TILE INSTALLATION OPTION...

Страница 5: ...ll Posts 2 2 Screws M4x3 8 PACK 2 3 Screw Cover Caps PACK 12 4 Screws M4x1 3 8 PACK 16 5 Screws M4x5 16 PACK 12 6 Spacer Blocks 2 7 Return Panel 1 8 Handle Set 1 9 Top Rollers 2 10 Water Deflectors 2...

Страница 6: ...of plumb up to 8mm Greater variances to plumb than 8mm at the wall must be assessed and adjusted because this impacts on the boundary line Preferably the door and return panel boundary line remains e...

Страница 7: ...t Plan Page 5 set up and plumb Wall Channels on boundary line 2 Apply silicone to back of wall channels and fasten to the wall ensuring that they remain plumb Tiling Note Some authorities do not allow...

Страница 8: ...17 Spacer Blocks 6 4 x 35mm screws 3 Two spacer Blocks 6 Two Glass clamps 16 and 2 screws 4 x1 0mm Note Refer back to Assembly Drawing on page XX to reference numbers 1 Bring the Door Frame together a...

Страница 9: ...orner joint together and drill and fasten this point 2 5 Align the door frame and return panel evenly to the walls and Tray 6 Square up the door frame 7 Fit door inserting top rollers into top rail an...

Страница 10: ...nd using GIB Aqualine 13mm or equivalent for both sides of the Alcove This is optimum width Measure outside boundary line at 15mm in from the outside of the Tray Mark the tray and plumb up the walls P...

Страница 11: ...terproof layer to be penetrated Use Bostik V60 to fix Wall Channels and allow to cure as per manufacturers instructions STEP 2 Assembly of Door Frame Components Top and bottom rails 13 Fixed front pan...

Страница 12: ...ite wall channel and fasten at the boundary line 4 Even out the door frame within each wall channel 5 Square up the door frame and door 6 Fit door inserting top rollers into top rail and push down bot...

Отзывы: