New Yorker CL3-091 Скачать руководство пользователя страница 31

1

iv

.  Stop feeding water to boiler but continue 

operating oil burner until excess water in 

boiler flows out through supply main and 
water lowers (by steaming) until it reaches 
normal level in boiler. Turn off oil burner. 
Drain boiler. Open all radiator valves. 
Reinstall all supply main air valves. Open 
gate valve in Hartford Loop.

v

.  When boiler has cooled down sufficiently 

(crown sheet of sections are not too hot to 
touch), close the drain valves at boiler and 
in return main and feed water slowly up to 
normal level in boiler. Turn on oil burner 
and allow boiler to steam for 10 minutes, 
then turn off burner. Draw off one quart of 

water from bottom gauge glass fitting and 
discard. Draw off another quart sample and 
if this sample is not clear, repeat the cycle 
of draining the boiler and return main and 

refilling the boiler until sample is clear.

vi

.  If the boiler water becomes dirty again 

at a later date due to additional sediment 
loosened up in the piping, close gate valve 
in Hartford Loop, open drain valve in 
return main, turn on oil burner and allow 

Condensate to flow to drain until it has run 
clear for at least 30 minutes while feeding 
water to boiler so as to maintain normal 
water level. Turn off oil burner, drain boiler, 
open gate valve in Hartford Loop, then 
repeat the full "Boiler and System Cleaning" 
procedure outlined in Paragraph B starting 
on Page 30.

e.  Make pH or Alkalinity Test.
 

After boiler and system have been cleaned and 

refilled as previously described, test the pH of 
the water in the system. This can easily be done 
by drawing a small sample of boiler water and 
testing with hydrion paper which is used in the 
same manner as litmus paper, except it gives 

specific readings. A color chart on the side of the 
small hydrion dispenser gives the reading in pH.  
Hydrion paper is inexpensive and obtainable 
from any chemical supply house or through your 
local druggist. The pH should be higher than 
7, but lower than 11. Add some of the washout 
chemical (caustic soda), if necessary, to bring the 

pH within the specified range.

f.  Boiler is now ready to be put into service.

2.  WATER BOILERS:

a.

 

Filling of boiler and system.

 

GENERAL 

— 

In a hot water heating system, 

the boiler and entire system (other than the 
expansion tank) must be full of water for 
satisfactory operation. Water should be added 
to the system until the boiler pressure gauge 
registers 12 psi. To insure that the system is full, 

NOTICE

Check  with  local  authorities  or  consult  local 
water treatment services for acceptable chemical 
cleaning compounds.

iii

.  Start burner and operate sufficiently to boil 

the water without producing steam pressure. 
Boil for about 5 hours. Open boiler feed 

pipe sufficiently to permit a steady trickle 
of water from the surface blow-off pipe. 
Continue this slow boiling and trickle of 

overflow for several hours until the water 

coming from the overflow is clear. 

iv

.  Stop burner and drain boiler in a manner 

and to a location that hot water can be 
discharged with safety.

v

.  Refill boiler to normal water line. If water 

in gauge glass does not appear to be clear, 
repeat steps (

i

. thru 

iii

.) and boil out the 

boiler for a longer time.

b.  Low pressure steam boilers such as the CL 

Series should be maintained with appropriate 
water treatment compounds.  Add suitable water 
treatment compounds as recommended by your 

qualified water treatment company.

c.  Remove temporary surface blow-off piping, plug 

tapping and reinstall safety valve. Boil or bring 
water temperature to 180°F promptly in order to 
drive off the dissolved gases in the fresh water.

d.  If unsteady water line, foaming or priming 

persist, install gate valve in Hartford Loop and 
drain valves in return main and at boiler as 
shown in Figure 9 and proceed as follows:

i

  Connect hoses from drain valves to floor 

drain. Close gate valve in Hartford Loop and 
open drain valve in return main.  Fill boiler 
to normal water level, turn on oil burner and 
operate boiler at this water level for at least 
30 minutes after the condensate begins to 
run hot, then turn off burner.

 

Close all radiator valves. Remove all supply 
main air valves and plug the openings in 
supply main.

ii.

  Draw about 5 gallons of hot water from 

boiler into a container and dissolve into it 
the appropriate amount of a recommended 
boilout compound. Remove safety valve 
from boiler and pour this solution into 
boiler, then reinstall safety valve.

iii

.  Turn on oil burner and keep operating while 

feeding water to boiler slowly. This will 
raise water level in boiler slowly so that 
water will be boiling hot and will rise slowly 
into supply main and back through return 

main, flowing from drain hose at about 
180°F. Continue until water runs clear from 
drain hose for at least 30 minutes.

Содержание CL3-091

Страница 1: ...b m u N l a i r e S d n a r e b m u N l e d o M r e l i o B e d i v o r p r e l i o b r e b m u N l e d o M r e l i o B r e b m u N l a i r e S r e l i o B e t a D n o i t a l l a t s n I L C r o t c...

Страница 2: ...onal Standard ANSI NFPA 31 Installation of Oil Burning Equipment for recommended installation practices B Current Edition of American National Standard ANSI NFPA 211 Chimneys Fireplaces Vents and Soli...

Страница 3: ...tely This boiler requires regular maintenance and service to operate safely Follow the instructions contained in this manual Installation maintenance and service must be performed only by an experienc...

Страница 4: ...ountered on floor around boiler 3 PROVIDE SERVICE CLEARANCE of at least 24 on top of boiler for cleaning flueways Provide at least 24 on right side of boiler for removal of rear tankless heater Provid...

Страница 5: ...Figure 1A CL3 Thru CL5 Water Boiler Less Tankless Heater Figure 1B CL3 Thru CL5 Water Boiler With Tankless Heater...

Страница 6: ...ransfer Surface Area Sq Ft A B C Rectangular Round CL3 17 3 8 8 1 4 5 7 8 8 x 8 x 15 6 x 15 16 14 33 CL4 22 3 8 10 7 8 6 7 8 8 x 8 x 15 7 x 15 20 20 90 CL5 27 3 8 13 3 8 7 7 8 8 x 8 x 15 8 x 15 24 27...

Страница 7: ...BH Water MBH Steam MBH Steam Sq Ft Round In Dia Rectangle In x In Height Ft Water Steam CL3 091 W 0 65 91 80 70 6 8 x 8 15 86 0 CL3 091 S 0 65 91 78 56 233 6 8 x 8 15 84 1 CL3 105 W 0 75 105 91 79 6 8...

Страница 8: ...is desired confirm the nozzle is the proper size and type refer to Table 9 then proceed to Item i below e If a lower input is desired remove the nozzle that was factory installed f Remove Beckett MD V...

Страница 9: ...curing h Loosen and remove the retaining nut and factory installed head bar from side of burner housing Install the proper head bar that corresponds to the desired firing rate refer to Table 9 and tig...

Страница 10: ...as factory pre set but must be checked at time of burner start up A pressure gauge is attached to the PRESSURE BLEEDER PORT 7 for pressure readings Two PIPE CONNECTORS 4 are supplied with the burner f...

Страница 11: ...ntrol bulb and insert bulb into immersion well Tighten clamp screws to secure control to immersion well Secure Figure 9 Recommended Boiler Piping for Series Loop Hot Water System control conduit to ja...

Страница 12: ...ply sealant and thread into NPT tapping on heater Apply heat transfer paste not furnished to control bulb and insert bulb into immersion well Tighten clamping screws to secure control to immersion wel...

Страница 13: ...f the boiler is to be operated in a system which has a large volume or excessive radiation where low boiler water temperature may be encountered i e converted gravity circulation system etc Install a...

Страница 14: ...sure safe proper operation of the boiler See Figure 13 for recommended installation 1 Install a draft regulator supplied by installer following the instructions furnished with the regulator See Figure...

Страница 15: ...eching or chimney In those extreme cases the chimney may have to be lined to insulate the chimney and thus prevent the condensation The addition of dilution air into the chimney may assist in drying t...

Страница 16: ...tions and joints Flared fittings are recommended Do not use compression fittings Open the air bleed valve and start the burner For clean bleed slip a 3 16 ID hose over the end of the bleed valve and b...

Страница 17: ...ed or the setting of the high limit is reached The circulator will operate as long as the thermostat is calling for heat If the thermostat is not satisfied and the high limit is reached the circulator...

Страница 18: ...18 Figure 17A Wiring Diagram for Water Boilers With Carlin EZ HP Burner and Split Controls Less Tankless Heater Figure 17B Wiring Diagram Water without Tankless Heater Riello Burner...

Страница 19: ...r heat if the boiler water temperature is up to the setting of the low limit in the L7224C control If boiler water temperature is below the low limit setting the burner will operate but the circulator...

Страница 20: ...20 Figure 18A Wiring Diagram for Water Boilers with Carlin EZ PH Burner and Split Controls with Tankless Heater Figure 18B Wiring Diagram Water with Rear Tankless Heater Riello Burner...

Страница 21: ...to its normal level The McDonnell Miller low water cut off incorporates a 10 second delay to prevent nuisance burner cut off due to rapid water level fluctuations The LWCO also has a time delay of 15...

Страница 22: ...am Steam Boilers With or Without Tankless Heater McDonnell Miller PS 801 Probe LWCO Carlin EZ HP Burner Figure 19B Wiring Diagram Steam with or without Tankless Heater Optional McDonnell Miller PS 801...

Страница 23: ...heaters Size the circulator and indirect water heater piping to obtain the boiler water flow through the indirect water heater called for by the indirect water heater manufacturer Refer to the indirec...

Страница 24: ...r from system Use the following procedure on a Series Loop System installed as per Figure 9 a Close all but one zone valve b Open drain valve on boiler c Open fill valve d Close purge valve e Open rel...

Страница 25: ...ree digit number i e 220 followed by F or C Pressing the I button again on L7224 models will display the Low Limit LL followed by a three digit number and the corresponding degree designator See Displ...

Страница 26: ...The High Limit automatically resets after the water temperature drops past the setpoint and through the Differential The L7248 models have High Limit Differential presets of 15 F 8 C The L7224 models...

Страница 27: ...essary see Table 9a a Remove pressure port bleeder plug from fuel pump and install Riello Combination Pressure Gauge and Bleeder Valve Assembly 5 OPEN ALL OIL LINE VALVES 6 Attach a plastic hose to fu...

Страница 28: ...OFF burner and remove Riello Combination Pressure Gauge and Bleeder Valve Assembly Install pressure port bleeder plug and tighten Start burner again 5 FLAME FAILURE The CL Series boiler controls oper...

Страница 29: ...pped with tankless heaters With burner off draw hot water until burner starts then turn off hot water and check burner shut down IF CONTROLS DO NOT MEET REQUIREMENTS AS OUTLINED ABOVE REPLACE CONTROL...

Страница 30: ...pipe threads of the probe to remove old hardened pipe dope and other foreign matter i Apply a moderate amount of good quality pipe dope to the pipe threads on the probe leaving the two end threads ba...

Страница 31: ...f water for satisfactory operation Water should be added to the system until the boiler pressure gauge registers 12 psi To insure that the system is full NOTICE Check with local authorities or consult...

Страница 32: ...the boiler the minerals fall out as sediment the salts coat the inside of the boiler and the oxygen escapes as a gas The accumulation of sediment eventually isolates the water from contacting the cast...

Страница 33: ...he chamber If the flame drags to the right or left sends sparklers upward or makes wet spots on the target wall the nozzle should be replaced If the condition persists look for fuel leaks air leaks wa...

Страница 34: ...l combustion chamber blanket and burner mounting plate insulation for signs of damage If damaged replace as needed E REASSEMBLE BOILER CAUTION Do not start the burner unless canopy smokepipe and burne...

Страница 35: ...Long sleeved loose fitting clothing 3 Gloves 4 Eye Protection Take steps to assure adequate ventilation Wash all exposed body areas gently with soap and water after contact Wash work clothes separatel...

Страница 36: ...provide lockout in the event of a stuck or welded motor relay NOTICE If flame is not established within 15 seconds of oil valve actuation known as Trial For Ignition TFI lockout will occur Lockout is...

Страница 37: ...Should you require assistance in locating a New Yorker Distributor in your area or have questions regarding the availability of New Yorker products or repair parts please contact New Yorker Boiler Co...

Страница 38: ...38 Bare Boiler Assembly Exploded View...

Страница 39: ...4 1 82020041 Combustion Chamber Liner 1 2 x 19 1 2 x 19 3 4 1 82020051 11 BSD Hinge Loop Bracket 2 2 2 100795 02 12 5 16 Flat Washer Plated 4 4 4 80860611 13 5 16 18 x 1 Lg Cap Screw Plated 2 2 2 8086...

Страница 40: ...acket Rear Panel Assembly 1 1 1 100820 01 3 Jacket Reversible Side Panel Assembly Non Heater Build 2 100821 03 2 100821 04 2 100821 05 With Heater Build 1 100821 03 1 100821 04 1 100821 05 4 Jacket Le...

Страница 41: ...Lo Limit Circ Relay 1 1 1 100059 01 100862 01 3 NPT x 1 Immersion Well Honeywell 123870A 1 1 1 80160426 4 2 Temperature Pressure Gauge 1 1 1 8056169 5 NPT x 7 Lg Nipple SCH 80 Black 1 1 1 100839 01 6...

Страница 42: ...1 806600508 4 Honeywell L4006A2015 Aquastat 1 1 1 80160400 5 123871A Immersion Well NPT 1 1 1 80160426 6 2 Dia Steam Gauge 1 1 1 8056010 7 10 Gauge Glass Set Conbraco 22 171 10 1 1 1 100854 01 7A Mal...

Страница 43: ...IL BURNER PARTS LIST MODEL AFG 60 Hz 3450 RPM FOR REPLACEMENT OIL BURNER PARTS CONTACT YOUR WHOLESALER OR THE BURNER MANUFACTURER R W BECKETT CORP P O BOX 1289 ELYRIA OHIO 44036 1 800 645 2876 Beckett...

Страница 44: ...4219 4219 4219 4219 4219 Electrode Insulator Assembly 5780 5780 5780 5780 5780 Spider Spacer Assembly 5653 5653 5653 5653 5653 Escutcheon Plate 3493 3493 Adjusting Plate Assembly 5941 5941 5941 Head 5...

Страница 45: ...city of piping for a probe LWCO How to Pipe A tee is commonly used to connect the probe LWCO to the supply or return piping as shown below LWCO Location manufacturers recommend an annual inspection of...

Страница 46: ...Bar Air Band GPH x Angle Type 2 Shipped CL3 091 0 65 EZ 1HP 0 50 0 55 0 55 x 70B Delavan p Loose 150 CL3 105 0 75 0 60 0 65 0 60 0 60 x 60ES Hago p Loose 150 p CL3 140 1 00 0 85 1 00 0 75 0 85 x 60B...

Страница 47: ...17 749 8292 Facsimile 617 740 2069 Toll Free outside Massachusetts 800 992 7637 Riello Canada Inc 2165 Meadowpine Blvd Mississauga Ontario L5N 6H6 Telephone 905 542 0303 Facsimile 905 542 1525 Toll Fr...

Страница 48: ...48 SERVICE RECORD DATE SERVICE PERFORMED...

Страница 49: ...49 SERVICE RECORD DATE SERVICE PERFORMED...

Страница 50: ...50 SERVICE RECORD DATE SERVICE PERFORMED...

Страница 51: ...51...

Страница 52: ...associated controls 6 Geographic Limitations These warranties apply only to boilers installed within the 48 contiguous United States 7 Installation Requirements In order for these warranties to be eff...

Отзывы: