V.  Maintenance and Service Instructions

A

.

 

MAINTENANCE  OF  LOW  WATER  CUT-
OFF  DEVICES

WARNING

Probe  and  float  type  low  water  cut-off  devices 

require annual inspection and maintenance.

1.   Although these devices are solid state in their 

operation, the probe is exposed to possible 
contamination in the boiler water and subject to 
fouling.

2.  It is important to physically remove the probe from 

the boiler tapping annually and inspect that probe 
for accumulation of scale or sediment.

3.  Follow these steps to inspect, clean and/or replace 

the probe:
a.  Turn off electric service to the boiler.
b.  Drain boiler water to a level below the tapping 

for the probe.

DANGER

Assure that the boiler is at zero pressure before 
removing  the  LWCO  probe.    Do  not  rely  on  the 
pressure  gauge  to  indicate  that  the  boiler  is  at 

zero  pressure.    Open  the  safety  valve  to  relieve 
all  internal  pressure  prior  to  proceeding.    Safety 
valve  discharge  piping  must  be  piped  such  that 
the potential for burns is eliminated.

c.  Disconnect wiring connections between the low 

water cut-off control and the probe.

d.  Remove the low water cut-off control from the 

probe.

e.  Unscrew the probe from the boiler tapping.
f.  Inspect that portion of the probe that is exposed 

to the boiler water for a scale or sediment 
buildup.

g.  Light deposits may be removed by wiping the 

probe with a damp cloth. Wiping the probe with 
a cloth soaked in vinegar will remove more 
tenacious lime deposits. The most stubborn 
deposits may be removed from the probe by 
using a diluted amount, 3 parts of water to 1 part 
of phosphoric acid (H

2

PO

4

).

CAUTION

Exercise caution when handling phosphoric acid 
and follow the instruction label on its container.

h.  Clean the pipe threads of the probe to remove 

old, hardened pipe dope and other foreign matter.

i.  Apply a moderate amount of good quality pipe 

dope to the pipe threads on the probe, leaving the 

two end threads bare. Do not use PTFE (Teflon) 
tape.

j.  Screw the probe into the boiler tapping.
k.  Mount the low water cut-off control on the 

probe.

l.  Reconnect the control to probe wiring.

m. Fill the boiler to its normal waterline.

n.  Add boiler water treatment compound as needed 

(refer to Paragraph B.).

o.  Restore electric service to the boiler.

p.  Fire burner to bring the water in the boiler to a 

boil to drive off free oxygen.

q.  WARNING — BEFORE  RETURNING  

BOILER TO  SERVICE:  Follow the low water 
cut-off check out procedure in Section IV. 
Operating & Service Instructions.

B.

  BOILER AND SYSTEM CLEANING 

INSTRUCTIONS FOR TROUBLE FREE 
OPERATION.

1.  STEAM BOILERS:

a.  Oil, greases & sediments which accumulate in a 

new boiler and piping must be removed from the 
system in order to prevent an unsteady water line 
and carry over of the water into the supply main 
above boiler.

 

Operate the boiler with steam in the entire 
system for a few days allowing the condensate 
to return to the boiler. If the condensate can 
temporarily be wasted, operate boiler only for 
the length of time it takes for condensate to run 
clear. If the latter cannot be achieved or if the 
condensate is returned to the boiler, boil out 
the boiler using the  SURFACE  BLOW-OFF  
connection.

i

Drain boiler until 1” of water is visible in 
gauge glass. Run temporary 1½” NPT pipe 
line from the surface blow-off connection to 
an open drain or some other location where 
hot water may be discharged safely. Do not 
install valve in this line.

ii

.  Drain about 5 gallons of hot water from 

boiler into a container and dissolve into it 
an appropriate amount of recommended boil 
out compound. Remove safety valve & add 
solution to boiler water thru exposed tapping 
using a funnel.

Содержание CL3-091

Страница 1: ...b m u N l a i r e S d n a r e b m u N l e d o M r e l i o B e d i v o r p r e l i o b r e b m u N l e d o M r e l i o B r e b m u N l a i r e S r e l i o B e t a D n o i t a l l a t s n I L C r o t c...

Страница 2: ...onal Standard ANSI NFPA 31 Installation of Oil Burning Equipment for recommended installation practices B Current Edition of American National Standard ANSI NFPA 211 Chimneys Fireplaces Vents and Soli...

Страница 3: ...tely This boiler requires regular maintenance and service to operate safely Follow the instructions contained in this manual Installation maintenance and service must be performed only by an experienc...

Страница 4: ...ountered on floor around boiler 3 PROVIDE SERVICE CLEARANCE of at least 24 on top of boiler for cleaning flueways Provide at least 24 on right side of boiler for removal of rear tankless heater Provid...

Страница 5: ...Figure 1A CL3 Thru CL5 Water Boiler Less Tankless Heater Figure 1B CL3 Thru CL5 Water Boiler With Tankless Heater...

Страница 6: ...ransfer Surface Area Sq Ft A B C Rectangular Round CL3 17 3 8 8 1 4 5 7 8 8 x 8 x 15 6 x 15 16 14 33 CL4 22 3 8 10 7 8 6 7 8 8 x 8 x 15 7 x 15 20 20 90 CL5 27 3 8 13 3 8 7 7 8 8 x 8 x 15 8 x 15 24 27...

Страница 7: ...BH Water MBH Steam MBH Steam Sq Ft Round In Dia Rectangle In x In Height Ft Water Steam CL3 091 W 0 65 91 80 70 6 8 x 8 15 86 0 CL3 091 S 0 65 91 78 56 233 6 8 x 8 15 84 1 CL3 105 W 0 75 105 91 79 6 8...

Страница 8: ...is desired confirm the nozzle is the proper size and type refer to Table 9 then proceed to Item i below e If a lower input is desired remove the nozzle that was factory installed f Remove Beckett MD V...

Страница 9: ...curing h Loosen and remove the retaining nut and factory installed head bar from side of burner housing Install the proper head bar that corresponds to the desired firing rate refer to Table 9 and tig...

Страница 10: ...as factory pre set but must be checked at time of burner start up A pressure gauge is attached to the PRESSURE BLEEDER PORT 7 for pressure readings Two PIPE CONNECTORS 4 are supplied with the burner f...

Страница 11: ...ntrol bulb and insert bulb into immersion well Tighten clamp screws to secure control to immersion well Secure Figure 9 Recommended Boiler Piping for Series Loop Hot Water System control conduit to ja...

Страница 12: ...ply sealant and thread into NPT tapping on heater Apply heat transfer paste not furnished to control bulb and insert bulb into immersion well Tighten clamping screws to secure control to immersion wel...

Страница 13: ...f the boiler is to be operated in a system which has a large volume or excessive radiation where low boiler water temperature may be encountered i e converted gravity circulation system etc Install a...

Страница 14: ...sure safe proper operation of the boiler See Figure 13 for recommended installation 1 Install a draft regulator supplied by installer following the instructions furnished with the regulator See Figure...

Страница 15: ...eching or chimney In those extreme cases the chimney may have to be lined to insulate the chimney and thus prevent the condensation The addition of dilution air into the chimney may assist in drying t...

Страница 16: ...tions and joints Flared fittings are recommended Do not use compression fittings Open the air bleed valve and start the burner For clean bleed slip a 3 16 ID hose over the end of the bleed valve and b...

Страница 17: ...ed or the setting of the high limit is reached The circulator will operate as long as the thermostat is calling for heat If the thermostat is not satisfied and the high limit is reached the circulator...

Страница 18: ...18 Figure 17A Wiring Diagram for Water Boilers With Carlin EZ HP Burner and Split Controls Less Tankless Heater Figure 17B Wiring Diagram Water without Tankless Heater Riello Burner...

Страница 19: ...r heat if the boiler water temperature is up to the setting of the low limit in the L7224C control If boiler water temperature is below the low limit setting the burner will operate but the circulator...

Страница 20: ...20 Figure 18A Wiring Diagram for Water Boilers with Carlin EZ PH Burner and Split Controls with Tankless Heater Figure 18B Wiring Diagram Water with Rear Tankless Heater Riello Burner...

Страница 21: ...to its normal level The McDonnell Miller low water cut off incorporates a 10 second delay to prevent nuisance burner cut off due to rapid water level fluctuations The LWCO also has a time delay of 15...

Страница 22: ...am Steam Boilers With or Without Tankless Heater McDonnell Miller PS 801 Probe LWCO Carlin EZ HP Burner Figure 19B Wiring Diagram Steam with or without Tankless Heater Optional McDonnell Miller PS 801...

Страница 23: ...heaters Size the circulator and indirect water heater piping to obtain the boiler water flow through the indirect water heater called for by the indirect water heater manufacturer Refer to the indirec...

Страница 24: ...r from system Use the following procedure on a Series Loop System installed as per Figure 9 a Close all but one zone valve b Open drain valve on boiler c Open fill valve d Close purge valve e Open rel...

Страница 25: ...ree digit number i e 220 followed by F or C Pressing the I button again on L7224 models will display the Low Limit LL followed by a three digit number and the corresponding degree designator See Displ...

Страница 26: ...The High Limit automatically resets after the water temperature drops past the setpoint and through the Differential The L7248 models have High Limit Differential presets of 15 F 8 C The L7224 models...

Страница 27: ...essary see Table 9a a Remove pressure port bleeder plug from fuel pump and install Riello Combination Pressure Gauge and Bleeder Valve Assembly 5 OPEN ALL OIL LINE VALVES 6 Attach a plastic hose to fu...

Страница 28: ...OFF burner and remove Riello Combination Pressure Gauge and Bleeder Valve Assembly Install pressure port bleeder plug and tighten Start burner again 5 FLAME FAILURE The CL Series boiler controls oper...

Страница 29: ...pped with tankless heaters With burner off draw hot water until burner starts then turn off hot water and check burner shut down IF CONTROLS DO NOT MEET REQUIREMENTS AS OUTLINED ABOVE REPLACE CONTROL...

Страница 30: ...pipe threads of the probe to remove old hardened pipe dope and other foreign matter i Apply a moderate amount of good quality pipe dope to the pipe threads on the probe leaving the two end threads ba...

Страница 31: ...f water for satisfactory operation Water should be added to the system until the boiler pressure gauge registers 12 psi To insure that the system is full NOTICE Check with local authorities or consult...

Страница 32: ...the boiler the minerals fall out as sediment the salts coat the inside of the boiler and the oxygen escapes as a gas The accumulation of sediment eventually isolates the water from contacting the cast...

Страница 33: ...he chamber If the flame drags to the right or left sends sparklers upward or makes wet spots on the target wall the nozzle should be replaced If the condition persists look for fuel leaks air leaks wa...

Страница 34: ...l combustion chamber blanket and burner mounting plate insulation for signs of damage If damaged replace as needed E REASSEMBLE BOILER CAUTION Do not start the burner unless canopy smokepipe and burne...

Страница 35: ...Long sleeved loose fitting clothing 3 Gloves 4 Eye Protection Take steps to assure adequate ventilation Wash all exposed body areas gently with soap and water after contact Wash work clothes separatel...

Страница 36: ...provide lockout in the event of a stuck or welded motor relay NOTICE If flame is not established within 15 seconds of oil valve actuation known as Trial For Ignition TFI lockout will occur Lockout is...

Страница 37: ...Should you require assistance in locating a New Yorker Distributor in your area or have questions regarding the availability of New Yorker products or repair parts please contact New Yorker Boiler Co...

Страница 38: ...38 Bare Boiler Assembly Exploded View...

Страница 39: ...4 1 82020041 Combustion Chamber Liner 1 2 x 19 1 2 x 19 3 4 1 82020051 11 BSD Hinge Loop Bracket 2 2 2 100795 02 12 5 16 Flat Washer Plated 4 4 4 80860611 13 5 16 18 x 1 Lg Cap Screw Plated 2 2 2 8086...

Страница 40: ...acket Rear Panel Assembly 1 1 1 100820 01 3 Jacket Reversible Side Panel Assembly Non Heater Build 2 100821 03 2 100821 04 2 100821 05 With Heater Build 1 100821 03 1 100821 04 1 100821 05 4 Jacket Le...

Страница 41: ...Lo Limit Circ Relay 1 1 1 100059 01 100862 01 3 NPT x 1 Immersion Well Honeywell 123870A 1 1 1 80160426 4 2 Temperature Pressure Gauge 1 1 1 8056169 5 NPT x 7 Lg Nipple SCH 80 Black 1 1 1 100839 01 6...

Страница 42: ...1 806600508 4 Honeywell L4006A2015 Aquastat 1 1 1 80160400 5 123871A Immersion Well NPT 1 1 1 80160426 6 2 Dia Steam Gauge 1 1 1 8056010 7 10 Gauge Glass Set Conbraco 22 171 10 1 1 1 100854 01 7A Mal...

Страница 43: ...IL BURNER PARTS LIST MODEL AFG 60 Hz 3450 RPM FOR REPLACEMENT OIL BURNER PARTS CONTACT YOUR WHOLESALER OR THE BURNER MANUFACTURER R W BECKETT CORP P O BOX 1289 ELYRIA OHIO 44036 1 800 645 2876 Beckett...

Страница 44: ...4219 4219 4219 4219 4219 Electrode Insulator Assembly 5780 5780 5780 5780 5780 Spider Spacer Assembly 5653 5653 5653 5653 5653 Escutcheon Plate 3493 3493 Adjusting Plate Assembly 5941 5941 5941 Head 5...

Страница 45: ...city of piping for a probe LWCO How to Pipe A tee is commonly used to connect the probe LWCO to the supply or return piping as shown below LWCO Location manufacturers recommend an annual inspection of...

Страница 46: ...Bar Air Band GPH x Angle Type 2 Shipped CL3 091 0 65 EZ 1HP 0 50 0 55 0 55 x 70B Delavan p Loose 150 CL3 105 0 75 0 60 0 65 0 60 0 60 x 60ES Hago p Loose 150 p CL3 140 1 00 0 85 1 00 0 75 0 85 x 60B...

Страница 47: ...17 749 8292 Facsimile 617 740 2069 Toll Free outside Massachusetts 800 992 7637 Riello Canada Inc 2165 Meadowpine Blvd Mississauga Ontario L5N 6H6 Telephone 905 542 0303 Facsimile 905 542 1525 Toll Fr...

Страница 48: ...48 SERVICE RECORD DATE SERVICE PERFORMED...

Страница 49: ...49 SERVICE RECORD DATE SERVICE PERFORMED...

Страница 50: ...50 SERVICE RECORD DATE SERVICE PERFORMED...

Страница 51: ...51...

Страница 52: ...associated controls 6 Geographic Limitations These warranties apply only to boilers installed within the 48 contiguous United States 7 Installation Requirements In order for these warranties to be eff...

Отзывы: