15. DRYER START-UP PROCEDURE
Do not allow the dryer to flow air unless powered up, switched on and cycling.
Resulting effect could be cartridge contamination; requiring replacement cartridges.
• Connect to mains power.
• Connect all pipe work, ensure inlet & outlet valves closed.
• Ensure the inlet operating pressure parameters are between 4-16 barg.
• Ensure the inlet air temperature is between 1.5°C - 50°C (35°F - 122°F).
• Turn on electrical power to the dryer.
• Slowly open inlet valve.
• The dryer will display its status and commence normal operation.
• Inspect dryer for leaks.
• Slowly open outlet valves.
• Leave in safe working condition before handing to customer.
Содержание 2 Series
Страница 1: ...MAINTENANCE SERVICE MANUAL www n psi com BREATHING AIR PURIFIER SERIES 2...
Страница 2: ...Document Issued Created Checked Revision 17 110 0491 05 11 2015 N McFall B Austin 0...
Страница 21: ...Page 21 14 MANIFOLD TIGHTENING SEQUENCES 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 Top manifold Bottom manifold...
Страница 26: ...Page 26 NOTES...
Страница 27: ......