English 6
concrete cement completely, and use anchor fastener bolt (expansion bolt)
in case of the hebel wall.
•
After selecting a proper location, determine the position of two holes that
are used for the installation of the expansion bolts with hook. Make two
holes on the wall by using a chopping bit with the depth matching to the size
of the expansion bolts that attached with the water heater. Then, insert the
bolts, turn the hook upwards, tighten the nuts to fix firmly, and then hang
the water heater on it.
•
Install the power socket in the wall. The requirements for the power socket are
as follows: 250V/10A, single phase, and three electrodes. It is recommended
to place the power socket on the top right of the water heater. The height of
the socket to the ground shall not be less than 1.8 m.
•
If the bathroom is too small, the water heater can be installed at another place
outside the bathroom. However, to reduce the heat loss caused by long
pipeline, the installation position should be as near as possible to the bathroom.
Expansion bolt with
hook
Ground
≥1.8 m
N (Blue)
E (Yellow/Green)
L (Brown)