background image

VSC8221 Evaluation Board

VPPD-03471 VSC8221 User Guide Revision 1.0

5

4

Quick Start

4.1

Board Configuration

Prior to powering the board, ensure that the jumpers and switches are in the following positions.

Table 1 • Switch and Jumper Configuration

Switch/Jumper

Position

J19 (MDC)

Jumper installed connecting F340 MDC to DUT MDC

J19 (MDIO)

Jumper installed connecting F340 MDIO to DUT MDIO

J14 (TRSTB)

Jumper installed connecting to GND. This is not required 
when R48 is installed.

J12 (XTAL1/REFCLK)

Jumper installed connecting center pin to XTAL.

J24 (PLL ENABLE/DISABLE)

Jumper installed connecting center pin to PLL ENABLE.

SW2

Hold in the left position during power-up and reset.

SW4

Slide to the left to use the on-chip regulator.

4.1.1

Clock and Reset

Power must be applied and the clock (either 25 MHz or 125 MHz) must be active at the correct 
frequency for the prescribed period of time in the datasheet before the RESETB pin is released. 
PLLMODE and OSCDISB pins are sampled during the device power-up or on assertion of RESETB pin.

The board will be shipped configured for use of the 25 MHz crystal thus OSCDISB must be pulled up and 
PLLMODE must be pulled down during power-up or assertion of RESETB by setting J24 to the PLL enable 
position and holding SW-2 in the 25 MHz position upon power-up.

4.1.2

Power Up

P5VDC to the board by plugging in the power cable (included in the kit) to J20. Two green LEDs 
should illuminate: D12 on the left side of the board indi3.3VDC present and D11 on the right side 
of the board indi1.2VDC present.

4.2

GUI and Driver Installation

Download the VSC8221EV GUI from Vitesse’s website onto a PC that has a USB port. Install the GUI by 
launching the setup.exe file. Once installed, connect the USB cable between the USB port of the PC and 
the USB connector (J16) on the evaluation board. Ensure the MDIO and MDC jumpers are properly 
placed from DUT to F340 on J23 to establish the connection between the VSC8221’s SMI pins and the 
SiLab F340.

USB communication is assisted by the Silabs USBXpress® drive. If not present on the PC, the user will 
need to download the USBXpress Development Kit from the Silicon Labs website (URL: 

http://www.

). Follow the installation directions after downloading 

silabs.com/products/mcu/Pages/USBXpress.aspx

the development kit.

To ensure the USBXpress driver is installed and properly recognizing the evaluation board, go to Control 
Panel and click on System>Hardware>Device Manager, and inspect the Universal Serial Bus controllers 
listed to see if “USBXpress Device” appears. The following figure shows that the PC recognizes that a 
USBXpress Device is connected.

Содержание VSC8221

Страница 1: ...VSC8221 User Guide VSC8221 Evaluation Board...

Страница 2: ...Clk Option 4 3 1 7 Silabs Microcontroller 4 3 1 8 EEPROM Option 4 3 1 9 CMODE Pins 4 3 1 10 CLOCKOUT SMA 4 3 2 Software Requirements 4 4 Quick Start 5 4 1 Board Configuration 5 4 1 1 Clock and Reset 5...

Страница 3: ...ision History The revision history describes the changes that were implemented in the document The changes are listed by revision starting with the most current publication 1 1 Revision 1 0 Revision 1...

Страница 4: ...o includes Vitesse s VeriPHY Cable Diagnostics feature This document describes the operation of the VSC8221 Evaluation Board VSC8221EV The Quick Start section describes how to install and run the grap...

Страница 5: ...en powered by a bench top supply the board may draw up to 3 A maximum module included 3 1 2 Copper Port RJ45 Connections The RJ45 copper media PHY port J1 uses a generic RJ45 jack with a discrete Puls...

Страница 6: ...etail on how to program the desired operating condition parameters through the CMODE configuration bits and how to choose the value of each CMODE pull up or pull down resistor 3 1 10 CLOCKOUT SMA The...

Страница 7: ...the PLL enable position and holding SW 2 in the 25 MHz position upon power up 4 1 2 Power Up Provide 5VDC to the board by plugging in the power cable included in the kit to J20 Two green LEDs should i...

Страница 8: ...tart Programs Vitesse Semiconductor Corp VSC8221_Evaluation_System icons The initial window will detect the attached USB devices automatically The following figure shows a typical EVB Connection windo...

Страница 9: ...the datasheet there are a number of internal registers that must be changed from their default value during device initialization Use this method to initialize the device by loading vsc8221_workaround...

Страница 10: ...onitor the link up bit in MII Register 1 bit 2 MII 1 2 read twice to update Traffic should now be flowing 4 5 Useful Registers 4 5 1 Ethernet Packet Generator ExtMII 29E is the Ethernet Packet Generat...

Страница 11: ...tion Board VPPD 03471 VSC8221 User Guide Revision 1 0 9 5 Additional Information For any additional information or questions regarding the device s mentioned in this document contact your local sales...

Страница 12: ...etermine suitability of any products and to test and verify the same The information provided by Microsemi hereunder is provided as is where is and with all faults and the entire risk associated with...

Отзывы: