Jacket assembly
1. Fit cast iron hinges(143) used for carrying front door onto front
section using 2 M8x30 setscrews (142) for each hinge.
Before assembly of front door (131), first decide the side of hinging
(for LH or RH opening). Screw hinge pins (141) into threaded holes.
Screw a M16 nut (49) onto each hinge pin as shown in figure below
left.
Hang the front door on M16 nuts. Position the front door up or
downwards by losening or tightening the M16 nuts.
2. There are two types of retarders. One is the second pass retarder (95) or (99) and the
other is the third pass retarder (for 4,5,6,7 sections) (97). Second pass retarders consist
of two stainless steel bladed modules (95 and 99). The modules are combined together
according to following table for preparing second pass retarders. Retarders are placed into
second and third flue gas passages of boiler as shown in following pictures:
In case of light or medium fuel-oil firing, the second pass retarders should not be used,
and input to boiler should be slightly reduced to values given in technical informations.
3. Fix front door to front section using four x M10x30
setscrews(136) and 10.5 washers(137).
4. Loosen the nuts on the front end of the upper staybolts(8) and
fit upper casing support (155) with its bend facing towards the rear
section. After mounting the front support sheet, ensure it to be
aligned parallel to the floor.
ASSEMBLY INSTRUCTIONS
Second pass retarder
modules
MD4 MD5 MD6 MD7 MD8 MD9
2 bladed module
2
1
3
bladed
module
1 2 2 2 2
Содержание Alpha Jetstream MD
Страница 3: ......
Страница 11: ......
Страница 20: ...ASSEMBLY INSTRUCTIONS...
Страница 23: ......
Страница 25: ...EXPLODED DRAWINGS MD JETSTREAM EXPLODED DRAWING BOILER GROUP...
Страница 26: ...EXPLODED DRAWINGS ALPHA JETSTREAM MD EXPLODED DRAWING INSULATION AND OUTER CASINGS...