3
Typical Panel Installation
(Type 1 or individual equipment installations may vary)
Use closest breaker to SPD Locate
SPD close to intended breaker
Keep Leads Short as Possible
Avoid Sharp Bends
Rotate
XP
Series
such that LED
indicator is most
visible
Outdoor installation requires
appropriate weather sealing
at the nipple
To Protected Loads
Figure 3
Leads: Short & Straight:
Cut excess; Do not coil or loop
Not Good
GOOD
X
Cut off Excess
Length
Do Not Loop
or Coil
Short &
Straight
Figure 4
INSTALLATION
:
Plan your installation and accomplish the following:
• Meet all National and Local codes (NEC
®
Article 285
and UL 1449 address SPDs).
•
Confirm System voltage to SPD voltage (120V SPD will
fail instantly on 240V, 277V, etc.).
• Mount STXP as close to panel or equipment as possible,
keeping leads as short as possible.
• Ensure leads are as short and straight as possible,
including neutral and ground. If using a breaker, use a
breaker position closest to SPD and panel’s neutral &
ground.
• If using a breaker, recommended breaker size is 30A
due to 10 AWG conductor.
• Make sure system is grounded per NEC
®
and clear of
faults before energizing SPD.
• Never Hi-Pot test any SPD. Product will fail prematurely.
• Do not install the STXP through the bottom of a NEMA
3R panel. Dripping water will prematurely fail the SPD.
(A sealed pipe nipple installed in the SPD may be a
solution.)
1. Use voltmeter to check voltages and ensure correct
SPD. See Data Sheet for specs & wire-outs.
2. Determine mounting method (See Figure 3) – weather
resistant equipment may be required.
3. If SPD has optional Dry Contact, pre-plan its installation.
4.
Remove power from panel/source. Confirm panel and
all sources are de-energized.
5. Identify breaker location and SPD location. Position
SPD such that LED is best visible.
6. Mount SPD – weather resistant applications require
additional sealing, o-rings, etc. (not included).
• Remove an appropriately sized knockout from panel.
• Connect conductors as appropriate – short and
straight as possible (Hi-Legs are Phase B).
7. Label or mark conductors as appropriate (Neutral: White,
Ground: Green, Energized: Black, Hi-Leg: Orange).
8. Make sure system is bonded per NEC
®
and is clear of
hazards or faults before energizing (N-G bonding not
per NEC
®
will fail SPDs: #1 cause of SPD failures).
9.
Energize and confirm proper operation of green LED
indicator and/or options.
Figure 5
V
WARNING
•
Confirm XO N-G Bonding at Upstream Transformer
•
Do Not Hi-Pot Test
•
Resulting Damage is not Covered Under Warranty
SPD
Hex Standoff
(4 Provided)
Mounting Surface
Mounting Screws
(4 Places, Not Provided)
Flush Mount Kit Screws
(8 Provided)
Phase,Ground,
Neutral Wires
Flush Mount Plate
Removed Material