background image

3

Typical Panel Installation

(Type 1 or individual equipment installations may vary)

Use closest breaker to SPD Locate 

SPD close to intended breaker

Keep Leads Short as Possible

Avoid Sharp Bends

Rotate 

XP

 Series 

such that LED 

indicator is most 

visible

Outdoor installation requires 

appropriate weather sealing 

at the nipple

To Protected Loads

Figure 3

Leads: Short & Straight: 

Cut excess; Do not coil or loop

Not Good

GOOD

X

Cut off Excess 

Length 

Do Not Loop 

or Coil

Short & 

Straight

Figure 4

INSTALLATION

:

Plan your installation and accomplish the following:

•  Meet all National and Local codes (NEC

®

 Article 285 

and UL 1449 address SPDs).

• 

Confirm System voltage to SPD voltage (120V SPD will 

fail instantly on 240V, 277V, etc.).

•  Mount STXP as close to panel or equipment as possible, 

keeping leads as short as possible. 

•  Ensure leads are as short and straight as possible, 

including neutral and ground. If using a breaker, use a 
breaker position closest to SPD and panel’s neutral & 
ground.

•  If using a breaker, recommended breaker size is 30A 

due to 10 AWG conductor.

•  Make sure system is grounded per NEC

®

 and clear of 

faults before energizing SPD.

•  Never Hi-Pot test any SPD. Product will fail prematurely.
•  Do not install the STXP through the bottom of a NEMA 

3R panel. Dripping water will prematurely fail the SPD. 
(A sealed pipe nipple installed in the SPD may be a 
solution.)

1.  Use voltmeter to check voltages and ensure correct 

SPD. See Data Sheet for specs & wire-outs.

2.  Determine mounting method (See Figure 3) – weather 

resistant equipment may be required.

3.  If SPD has optional Dry Contact, pre-plan its installation.
4. 

Remove power from panel/source. Confirm panel and 

all sources are de-energized.

5.  Identify breaker location and SPD location. Position 

SPD such that LED is best visible.

6.  Mount SPD – weather resistant applications require 

additional sealing, o-rings, etc. (not included).
•  Remove an appropriately sized knockout from panel.
•  Connect conductors as appropriate – short and 

straight as possible (Hi-Legs are Phase B).

7.  Label or mark conductors as appropriate (Neutral: White, 

Ground: Green, Energized: Black, Hi-Leg: Orange).

8.  Make sure system is bonded per NEC

®

 and is clear of 

hazards or faults before energizing (N-G bonding not 
per NEC

®

 will fail SPDs: #1 cause of SPD failures).

9. 

Energize and confirm proper operation of green LED 

indicator and/or options.

Figure 5

V

WARNING

• 

Confirm XO N-G Bonding at Upstream Transformer

• 

Do Not Hi-Pot Test

• 

Resulting Damage is not Covered Under Warranty

 

SPD

Hex Standoff

(4 Provided)

Mounting Surface

Mounting Screws

(4 Places, Not Provided)

Flush Mount Kit Screws

(8 Provided)

Phase,Ground,

Neutral Wires

Flush Mount Plate

Removed Material