Figure 6: Packing the 4036/2036 Switch
6.
Insert the switch into the cardboard box and place it on the bottom foam.
7.
Place the top foam on top of the switch.
8.
Slide the rail kit box in the dedicated niche alongside of the switch, as shown in
the
illustration in Unpacking the Switch
(on page
59
).
IMPORTANT NOTE:
When sending the switch for repair without the rail kit, it is still
important to secure the switch by filling this niche with a filler. This will protect the switch
and prevent it from moving during transportation.
9.
Place the Getting Started Guide and the Multipurpose Console Kit (Mng)
on top
of the top
foam as shown in
the illustration in Unpacking the Switch
(on page
59
).
10.
Place the power cords in the allocated spaces in the foam, as shown in
the illustration in
Unpacking the Switch
(on page
59
).
11.
Use tape to close the box and verify that the box is securely closed.