7. Operating instructions
7.4 Shut-off
The shut-off with a plastic handle (see Fig.) has a square-end connection (see Fig.) under the handle after it has been pulled down. If the handle has been
removed, this square-end connection can be turned with an appropriate socket wrench, thus opening or closing the shut-off. The opening angle of the
shut-off is also visible, i.e. whether it is open or closed. Check the opening angle during the commissioning. The full opening of the shut-off is shown in
the illustration.
Marking on the spindle
(fully open)
7.5 Manual air bleed device
A manual air bleed device (see Fig.) is located on the heat exchanger inlet on the
primary side (heating medium) for manually bleeding the heat exchanger (primary side).
Please only use a suitable tool to open the air vent! The flushing, filling and bleeding
of the system must be carried out professionally before the commissioning to ensure
that it operates properly.
7.6 Additional information regarding the installation and commissioning
Dirt traps to protect systems are provided in the station inlet if required.
•
Commission the system once the station has been flushed and filled and a pressure test has been carried out.
•
All installations on the heating and domestic water side must be complete.
•
Bleed the system every so often during the commissioning process (heat exchanger above the manual bleed device at the rear/top)
•
Please refer to the LogoFresh XL-Line 100/120 operating instructions for the commissioning
•
Please observe the "Checklist" chapter.
•
The controller can only be actuated through the "Controller function" switch if the system has been put into operation correctly.