It is essential that the installation is carried out in the order given
below to ensure the correct operation of the system.
First read the system description sheet before following the
instructions below
1.
Connect the Control valve twin & earth to the marked terminals.
2.
Connect BMS, beacons, sounders etc to the relay outputs.
3.
Connect any additional EM stop buttons and thermal links in series to the terminals marked “EM STOP”.
4.
Each detector has a rotary address switch and each switch should be set to address’s “1” or “2”, then connected
to the appropriate gas detector terminal marked “detector 1” or “detector 2”on the panel.
5.
Enable the detector channels (1 or 2) as being used by with switch (
12
) Connect the 3 amp fused spur 240 volt
supply to marked terminals.
6.
Once power is connected to the panel the detectors will flash the green LED’s for 90 seconds after which the LED’s
will be on continuously.
7.
At this point press the reset switch and the control valve will open and the system in now running.
Checklist
AGDS-2
Please do not hesitate to call for advice on the
following numbers:
0161 233 0600 office hours
Or out of hours call:
Notes.
It is recommended that all systems are commissioned a er installa on by Medem UK. This will extend the warranty period from 5
years to 10 years and ensure the system is working as designed.
Please see warranty condi ons that came with the main panel