background image

13/12/2017 

It is essential that the installation is carried out in the order given  

below to ensure the correct operation of the system. 

 

First read the system description sheet before following the  

instructions below 

 
1. 

Connect the Control valve twin & earth to the marked terminals. 

2. 

Connect BMS, beacons, sounders etc to the relay outputs. 

3. 

Connect any additional EM stop buttons and thermal links in series to the terminals marked “EM STOP”.   

4. 

Each detector has a rotary address switch and each switch should be set to address’s “1” or “2”, then connected 

to the appropriate gas detector terminal marked “detector 1” or “detector 2”on the panel.  

5. 

Enable the detector channels (1 or 2) as being used by with switch (

12

) Connect the 3 amp fused spur 240 volt 

supply to marked terminals. 

6. 

Once power is connected to the panel the detectors will flash the green LED’s for 90 seconds after which the LED’s 

will be on continuously. 

7. 

At this point press the reset switch and the control valve will open and the system in now running.  

Checklist 

 

AGDS-2 

Please do not hesitate to call for advice on the  

following numbers: 

0161 233 0600 office hours 

Or out of hours call: 

Notes. 

It is recommended that all systems are commissioned a er installa on by Medem UK. This will extend the warranty period from 5 

years to 10 years and ensure the system is working as designed.  

Please see warranty condi ons that came with the main panel 

Содержание AGDS-2

Страница 1: ...alled and commissioned to the satisfaction of the manufacturer A commissioning certificate must be issued to the end user along with instructions for the operation of the equipment As the Manufacturer...

Страница 2: ...gh alarm Carbon Monoxide detectors are pre calibrated at 80ppm pre alarm and 100ppm for high alarm Connect a detector to either the detector 1 terminals 6 7 or detector 2 terminals 8 9 each detector h...

Страница 3: ...connection Reset 12 Enable Detectors Channels enable a channel when it has a detector connected 13 High alarm time delay function Controls the length of time between a High alarm and the closing of th...

Страница 4: ...be followed with reference to running low and mains voltage cables together The maximum cable length between a detector and the control panel should not exceed 100 metres if the distance between the...

Страница 5: ...ould be wired in series with the EM stop buttons To EM Stop connections in the panel Indicator bar shows when pressed Normal EM Stop Activated Multiple Stop Buttons Single Stop Buttons Resetting indic...

Страница 6: ...s that is being monitored for See the gas detectors own instructions for more guidance AGDS 2 Detector Information VE supply Comm s From either the main panel Address Selector The selector must be set...

Страница 7: ...ng head height and between 1m and 3m from the potential source Care should be taken so they are not located close to the edge of a canopy or in direct flow of the supply or extract ventilation For add...

Страница 8: ...lier Medem UK will exchange faulty valves for return to the manufacturer 5 Where a Medem UK engineer or another company appointed by Medem UK commission and installed system then that system will carr...

Страница 9: ...ector 1 or detector 2 on the panel 5 Enable the detector channels 1 or 2 as being used by with switch 12 Connect the 3 amp fused spur 240 volt supply to marked terminals 6 Once power is connected to t...