PROCEDURE FOR EXTERNAL
INSTALLATIONS
If the enclosure for the ZC cabinet is to be erected
outside the house, the shielding and flue installation
details above will still apply. Suitable foundations will
be required to support the weight of the enclosure and
the heater, and weatherproofing for the entire
assembly will be necessary.
As before, the opening in the wall for the appliance
must be 710mm wide and 735mm high, with its bottom
edge level with the floor of the room. The minimum
clearances to nearby side walls and the mantleshelf
clearances detailed in Fig. 2 must be complied with.
OPERATING INSTRUCTIONS
Before operating this appliance, proceed through the
following checklist.
1) Read and understand these instructions before
operating this appliance.
2) Check to see that all wiring is correct and enclosed
to prevent possible shock.
3) Check to ensure there are no gas leaks.
4) Never operate the appliance with the glass
removed.
5) Verify that the flue and the flue cap are
unobstructed.
6) Verify log placement. If the pilot or ignition
electrodes cannot be seen when lighting the unit -
the logs or the embers have been incorrectly
positioned.
7) The heater should never be turned off and on
again without a minimum of a 60-second wait.
8) Each time the appliance is lit, condensation will fog
the glass. This condensation is normal and will
disappear in a few minutes as the glass heats up.
DO NOT USE THE HEATER WITH THE GLASS
ASSEMBLY REMOVED.
OPERATING PROCEDURE
PICCOLO - LIGHTING
IMPORTANT: The gas control knob cannot be
turned from "PILOT" to "OFF" unless it is partially
depressed.
1) If the control knob is in the "OFF" position proceed
to Step 4.
2) Push in gas control knob and turn clockwise to
"OFF". Knob cannot be turned from "PILOT" to
"OFF" unless knob is pushed in. Do not force.
3) Wait five minutes to allow gas that may have
accumulated in the main burner compartment, to
escape. If you do smell gas, follow the instructions
on the front of this manual. If you don't smell gas
continue on to the next step.
4) Push in and turn the gas control counter clockwise
to "IGN".
5) The piezo igniter will click as a spark jumps across
the terminals at the pilot. It may be necessary to
repeat this several times before the pilot ignites if
there is air in the pilot light pipeline. The pilot is
located at the right, inside the firebox behind the
front log. When the pilot lights, continue to hold
the control knob in for approximately 15 seconds,
then release it. The pilot flame should continue to
burn. If the pilot does not remain lit, repeat this
operation, allowing a longer period before
releasing the gas control knob.
6) With the pilot flame established, turn the gas
control knob fully anticlockwise to ignite the burner.
The flame height can then be adjusted as required
by turning the knob clockwise.