Installation 

M&C SP180-H probes are designed for stationary use. The professional choice of the right sample probe for the 
application and the professional installation garantees a long service life and minimum maintenance work. The 

ideal position for mounting the sample probe is horizontally with a tilt angle of 10% towards the process. Please 
follow these installation steps and see details in Figure 2. 

 

Screw the sample probe tube directly into the ¾" inner thread 

 of the probe flange and tighten it. 

 

To mount the SP180-H at the sampling flange, please loosen the metal clamp 

 around the heat insulating 

protection cover and remove the cover 

.  

 

If the probe connection is not the same size as the standard flange connection DN65 PN6, an adapter flange 

 (optional) should be mounted to the probe (see Figure 2). Place the gasket 

 between the adapter 

flange and the probe flange. 

 

If the heated probe tube type SP30/35 is used then the probe is to be screwed to its flange (with welded 
threaded bolt). First insert the flange seal 

 between the two flanges. 

 

Attach the flange seal 

 to the probe connection. 

 

Insert sample probe with mounted probe tube into the connection piece and fasten the probe using the 
supplied bolts and nuts. 

 

After mounting of the probe at the sampling flange put the heat insulating protection cover 

 over the 

probe flange again and secure it with the metal clamp 

.  

 

Note 

For the preferred mounting position of the probe, the sample gas 
outlet is pointing downwards. This is just the preferred mounting 
position, it is not necessary for correct operation.  

 

Figure 2 

 

Mounting of the SP180-H 

 

Содержание SP180-H

Страница 1: ...Compact Gas Sample Probe Series SP SP180 H Instruction Manual Version 1 03 01...

Страница 2: ...of this manual For additional information about our products and our company please go to M C s website www mc techgroup com There you will find the data sheets and manuals of all our products in Germ...

Страница 3: ...g the sample probe 11 12 Preparation for Installation 11 13 Installation 12 13 1 Connecting the heated sample line 13 13 2 Connecting the test gas line 13 14 Electrical Connection 14 15 Starting up 15...

Страница 4: ...t by qualified personnel Please follow all instructions and warnings closely Please read this manual carefully before commissioning and operating the device If you have any questions regarding the pro...

Страница 5: ...s are disconnected Operate the device only in the permitted temperature and pressure ranges For details please refer to the technical data sheet or manual Install the device only in protected areas sh...

Страница 6: ...mage to property can occur if the appropriate safety precautions are not observed Attention Attention indicates that an unintended result or situation can occur if the corresponding information is not...

Страница 7: ...itions and to measurement work is a necessary condition for a measurement system to work smoothly Basically the gas sample should be kept to a necessary minimum This is made possible thanks to optimis...

Страница 8: ...ok tube connector Power supply 110 V AC up to 240 V 50 60 Hz Power consumption Start up 400 VA usual 100 VA fuse 6 A Electrical connection Terminals max 2 5 mm2 cable fittings 1 x M20 x 1 5 and 1 x M1...

Страница 9: ...tallation reliable operation and trouble free maintenance Advantages are Gas sampling with dust laden processes low volume fast response time filter elements can be changed without tools and without d...

Страница 10: ...order to select an appropriate heated M C sample line for your application The sample gas outlet at the probe is designed for a 6 mm DN4 6 tube The stainless steel sampling tube of one meter length pa...

Страница 11: ...eds to be easily accessible for all necessary maintenance work The temperature of the sample probe connections needs to be always above the acid dew point in order to avoid corrosion and problems with...

Страница 12: ...the same size as the standard flange connection DN65 PN6 an adapter flange optional should be mounted to the probe see Figure 2 Place the gasket between the adapter flange and the probe flange If the...

Страница 13: ...e nut of this connector then use a flat spanner to turn the nut exactly 1 turns The nut is now correctly mounted Place the heated sample line into the open metal clamp and close the clamp Note Make su...

Страница 14: ...Data on page 8 We recommend to use a low temperature alarm at all times In case of an alarm the flow can be stopped and the components downstream of the probe will be protected The junction box is mo...

Страница 15: ...nd standards Warning Disconnect power supply before opening the device for access Make sure that all external power supplies are disconnected This also applies to any external alarm or control circuit...

Страница 16: ...lamp against the studs and turn the handle to the left until the filter lid loosens Unscrew the knurled head thumb screw of the filter and remove the filter element Check the seals of the filter eleme...

Страница 17: ...the sample probe Figure 5 Replacing the filter element 17 Decommisioning Before decommissioning the gas sample probe turning off the heating the probe needs to be flushed with inert gas or air in ord...

Страница 18: ...6 12 18 93S0045 Viton gasket 30 R 4 8 12 93S0020 O ring lid sealing 39 Material Viton R 2 4 6 93S0025 O ring lid sealing 55 Material Viton R 2 4 8 90S2080 Novapress gasket 3 4 blue max 600 C 1112 F R...

Отзывы: