NOTE
:
The BAT+ of the UPS connect poles is connected to the anode of the positive battery, the BAT-N
is connected to the cathode of the positive battery and the anode of the negative battery, the
BAT- is connected to the cathode of the negative battery.
Factory setting of the long-run unit is battery quantity---32pcs, battery capacity---12V65AH.
When connecting 32/34/38/40 batteries, please re-set desired battery quantity and its capacity
after UPS starts at AC mode. Charger current could be adjusted automatically according to
battery capacity selected. All related settings can be done through LCD panel or monitoring
software.
CAUTION!
Ensure correct polarity battery string series connection. I.e. inter-tier and inter
block connections are from (+) to (-) terminals.
Don’t mix batteries with different capacity or different brands, or even mix up
new and old batteries, either.
WARNING!
Ensure correct polarity of string end connections to the Battery Circuit
Breaker and from the Battery Circuit Breaker to the UPS terminals i.e. (+) to
(+) / (-) to (-) but disconnect one or more battery cell links in each tier. Do
not reconnect these links and do not close the battery circuit breaker unless
authorized by the commissioning engineer.