  7    

Hitching to the tractor

ALWAYS OPERATE ON LEVEL GROUND WHEN HITCHING/UNHITCHING THE IMPLEMENT. THIS WILL

PREVENT DANGEROUS MOVEMENT. NVER ALLOW ANYONE TO STAND BETWEEN THE TRACTOR

AND THE MACHINE.

1.  Reverse the tractor,

2.  Ensure the tractor parking brake is applied

3.  Connect the lower link arms & Top Link. Secure both in position with correct size pin.

4.  Fit the PTO shaft & secure the PTO cover chains.

5.  Check all guarding is present & secured.

6. 

Transport Position

1.  Check machine is hitched to the tractor as described.  

2.  Ensure the tractor parking brake is applied

3.  Lift the machine into transport position.

Maintenance

The machine must always be disconnected from the tractor before any cleaning, lubricating and servicing operations 

can be carried out. Ensure that the Rear and Side decks are locked up while performing maintenance.  If emergency 

operations are required whilst the machine is connected to the tractor, switch off the engine, engage the parking brake 

and disengage the PTO.  Good, regular maintenance and correct use are essential if the grass topper is to remain 

safe and long lasting.  

NOTE:  Maintenance must be carried out by qualified personnel. 

Greasing schedule

Please grease the following:

Initially

After 8 hours work

PTO Shafts

Lubricate moveable mechanical joints when required.  All nuts and bolts in the transmission including PTO shafts and 

gearboxes should be checked for tightness after mowing at the following intervals:

•  1st 50 acres

•  1st 100 acres

•  1st 250 acres and every 250 acres thereafter

Operating the Machine/Mowing

The MAJOR Pasture Topper is designed to operate at a max 540 rpm (1000 RPM Jungle Buster. Always operate on 

level ground when hitching / unhitching the implement. This will prevent dangerous movement. Never allow anyone to 

stand between the tractor and the pasture topper.

1.  Ensure the machine is hitched correctly to the tractor as previously described.

2.  Ensure bystanders are clear from the machine & cannot be hit with debris expelled from the machine.

3.  Ensure cutting decks are lowered to the ground.

4.  Start up the tractor PTO at a low RPM.

5.  Build up to operating speed, select a suitable forward gear & proceed to cut grass.

Содержание 601SL

Страница 1: ...MAJOR GRASS SLASHERS JUNGLE BUSTER Operator Manual Parts List...

Страница 2: ...31 0 6389 19585 Email euinfo major equipment com Web www major equipment com Find us on FACEBOOK MAJOR MACHINERY View our channel MAJOREQUIPMENT Disclaimer While every effort has been made in the prod...

Страница 3: ...Safely 2 Workstation 3 Regulations for use of the transmission 3 PTO Shaft Safety 3 Hazards 4 Driving safely on public roads 4 Operating the Machine Inspections before Use 5 Key to Main Parts 6 Start...

Страница 4: ...2007 Safety Health and Welfare at Work General Application Regulations 2007 Ireland Health Safety at Work etc Act 1974 c 37 UK EN ISO 14121 1 2007 Safety of machinery Principles for risk assessment EN...

Страница 5: ...s booklet and driven by an adequate drive line of the tractor PTO All other use is strictly prohibited Product Identification Machine Serial Numbers If you need to contact MAJOR or your MAJOR dealer f...

Страница 6: ...d PTO entanglement hazard keep clear of PTO drives Safety Machine Safety Labels The machine safety labels shown in this section are placed in important areas on your machine to draw attention to poten...

Страница 7: ...ment and attempt to clean or adjust a machine before components have completely stopped moving Shear bolt protection device in PTO shaft shears the mowing parts are still spinning but the primary PTO...

Страница 8: ...nd the wings need to be raised lowered the operator must not leave the tractor Always ensure the PTO has been turned off and the parking brake applied before leaving the tractor cab or carrying out ma...

Страница 9: ...shaft is too long it should be shortened in the following way Set the machine at a minimum distance from the tractor then brake the tractor and switch off the engine Separate the two halves of the PT...

Страница 10: ...ck tightness of all nuts bolts and retaining screws after the first and second hours of work 7 Ensure safety guards and flaps are in place at all times where fitted 8 Due to the corrosive nature of gr...

Страница 11: ...PTO Good regular maintenance and correct use are essential if the grass topper is to remain safe and long lasting NOTE Maintenance must be carried out by qualified personnel Greasing schedule Please g...

Страница 12: ...ient oil in gearbox Check oil level and top up as necessary Incorrect PTO R P M rate Check PTO R P M and adjust as necessary Excessive vibration Loose parts Check all bolts are fully tightened Incorre...

Страница 13: ...WASHER 4 26 T40BO 1100 PTO Shaft 601 Slasher 1 27 12T BBS BLADE BACK SPACER 2 28 8SM9 3 Spacer 8 Item Part No Description Qty 1 1 2F 1 2 Nyloc Nut 12 2 12x212FBZP 1 2 x2 1 2 FINE BOLT 4 3 8SM9 2 BLADE...

Страница 14: ...R 4 11 FWM20 M20 Flat Washer 4 12 GM2 STANDARD A FRAME 1 13 M12 M12 NYLOC NUT 13 Item Part No Description Qty 14 M12x30SZP M12x30 SET BOLT 10 15 M12x35BZP M12x35 BOLT 3 16 M20 M20 NYLOC NUT 2 17 M20x1...

Страница 15: ...16 NYLOC NUT 8 19 M16x40SZP M16x40 SET BOLT 8 20 M20 M20 NYLOC NUT 6 21 M20x130BZP M20x130 BOLT 2 22 M6 M6 NYLOC NUT 8 23 M8x16 M8x16 SET BOLT 4 24 112 CAT 2 PIN DIA 28 5x159mm 2 25 1373 M8xDIA 9 U BO...

Страница 16: ...1 4 FINE BOLT 4 9 EW29A 5 8 D SHACKLE 3 10 FWM12 M12 FLAT WASHER 18 11 FWM20 M20 FLAT WASHER 4 12 GM2 STANDARD A FRAME 1 13 M12 M12 NYLOC NUT 26 14 M12x120BZP M12x120 BOLT 4 15 M12x30SZP M12x30 SET B...

Страница 17: ...OFFSET 2 8 T501160CEC12B02 T50 SHEAR BOLT 1 9 199209 DIA 50 5 54mm INSERT 2 10 199211 SQ 52 54mm INSERT POL 2 11 5 8F 5 8 FINE NYLOC NUT 4 12 58x214FBZP 5 8 x2 1 4 FINE BOLT 4 13 81 CAT 2 PIN DIA 25 4...

Страница 18: ...x2 1 2 FINE BOLT 4 3 6SL NB BLADE BACK 925 CTR 2 4 9GT USS UNDER SOLE SKID 1 5 BLD 51535 609 SLASHER BLADE 2 7 DSW45 DISC SPRING 45x22 4x2 5 5 8 FW12 12 FLAT WASHER 2 9 M20 M20 NYLOC NUT 2 10 M20x60B...

Страница 19: ...DP 8 16 1 11 0 139 7100 00 PROTECTIVE WASHER 1 12 8 7 1 01107 DOUBLE LIP SEAL 50X90X10 1 Item Part No Description Qty 13 0 149 5000 00 GEAR Z20 M6 25 2 14 8 0 9 00469 BEARING 30210 1 15 0 244 7500 00...

Страница 20: ...35 1 8 2 2 00515 Castle Nut 1 12 LF135 2 8 3 2 00409 Washer 1 13 LF135 19 8 4 1 00993 Key 1 14 M10x20SZP 8 11 00054 Bolt 1 15 LF135 6 8 5 1 00030 Snap Ring 1 16 LF135 3 8 5 3 00955 Snap Ring 1 Item Pa...

Страница 21: ...00 00 Protective Flat Washer 40 4x79 9x1 1 15 8 7 1 00748 Dust Lip 40x80x12 1 16 8 0 9 01049 Roller Bearing 30306 30x72x20 75 1 Item Part No Description Qty 17 8 0 9 00024 Roller Bearing 30208 40x80x1...

Страница 22: ...manship or parts with the exception of components not of MAJOR S manufacture or design i e hydraulic components universally jointed shafts chains and tyres etc which are subject to the original manufa...

Страница 23: ...s Co Mayo Ireland Tel 353 0 9496 30572 UK OFFICE Major Equipment Ltd Major Ind Estate Heysham Lancs LA3 3JJ UK Tel 44 0 1524 850501 Netherlands Germany OFFICE Major Equipment Intl Ltd Postbus 29 NL 77...

Отзывы: