SHR Series  Woodburning Fireplaces

20001384

Framing

Framing can be constructed before or after the fireplace
is set in place, however, most installers build the frame
before setting the fireplace.

Frame fireplace with 2 x 4 lumber or heavier materials.
Refer to framing dimensions in Figures 1 - 4  for basic
fireplace specifications.

NOTE:  Framing should be positioned to accommodate
wall covering and fireplace facing material.

Firebrick Installation

For the SHR52 model the firebrick is packed separately
and must be installed in the fireplace.

You will need four (4) firebrick, three (3) brick retainers,
a phillips head screwdriver, and the grate.

The side and rear firebrick each have a notch in the top
of the brick panel. The side firebrick have a notch in the
lower front side of each panel. The herringbone pattern
faces out of the fireplace always. (Fig. 11)

NOTE: The screens and screen rod smoke baffle
assembly must be removed and set aside before
proceeding. Remove the two screws holding the
screens place. There are seven screws holding the
screen rod smoke baffle in place.

1. Remove the three brick retainers from the combus-
tion dome by removing the phillips screws, set aside.

2. Set the left firebrick in place on the left side of the
fireplace.

3. Slide the rear firebrick back into the left corner
behind the end of the left firebrick. Push both panels
back as far as possible into the left side and corner.

4. Swing the right side of the back firebrick into place.
Attach the left brick in place using a brick retainer at the
top and phillips screw removed earlier.

5. Slide the right firebrick into place as far back as
possible. Attach rear firebrick and right firebrick using
brick retainers and phillips screws removed earlier.

6. Slide the hearth firebrick into the grate clip. (Fig. 12)
The grate will be used as a handle to set the hearth
firebrick in place.

7. With the hearth firebrick securely in place in the
grate clip, carefully lift the hearth firebrick into the
fireplace, set the rear of the firebrick down, then slide
back to meet the rear firebrick. Gently set the front of
the firebrick in place.  Replace screens and screen rod
smoke baffle assembly.

FP555SHR

Fig. 10  Insulating between platform and fireplace.

Hard, Flat
Surface

Insulation

Platform

Rear Firebrick

Brick
Retainer

Side Firebrick

Front
Notch

FP1234

Fig. 11  SHR52 Firebrick installation.

Chimney Set-up

Since you have already preplanned the chimney run,
you should know exactly how the installation is to be
accomplished — how much pipe is required, the
number of elbows, if any, and type of termination to be
used.

Grate

Grate Clip

Hearth
Firebrick

FP1235

Fig. 12  Hearth firebrick in place in grate clip.

Содержание SHR36

Страница 1: ...ls SHR36 SHR42A SHR48 SHR52 Underwriter s Laboratories Report No MH6018 DO NOT DISCARD THIS MANUAL Retain for future use 20001384 7 04 Rev 13 410 Admiral Blvd Mississauga Ontario Canada L5T 2N6 905 67...

Страница 2: ...CFM Spe cialty Home Products in combination or assembly with a Majestic Fireplaces fireplace system notwithstanding any independent testing laboratory or other third party ap proval of such component...

Страница 3: ...ine Access Gas Line Access 1365mm FP546A Fig 2 SHR42A Series specifications and framing SHR42A Series Woodburning Fireplace 36 914mm 46 1175mm 44 1118mm 24 610mm 7 189mm 13 Dia 340mm Rough Opening Wid...

Страница 4: ...Access Gas Line Access 1518mm SHR48 Series Woodburning Fireplace Fig 3 SHR48 Series specifications and framing FP545A 9 235mm 52 1321mm 62 1584mm 52 1334mm 33 838mm 7 189mm 13 Dia Rough Opening Width...

Страница 5: ...ion FP554A Fig 5 Fireplace and chase parts identification SHR48 shown Termination Cap Storm Collar Pan Flashing Batt Insulation cut out around firestop Firestop Ceiling Level Draftstop Ledge Bracket S...

Страница 6: ...measured from the hearth to the chimney exit SHR36 SHR42A SHR48 SHR52 Max 90 90 90 90 Min 0 Elbows 14 6 14 6 16 0 16 0 2 Elbows 15 6 15 6 19 0 19 0 4 Elbows 21 0 21 0 24 0 24 0 B Do not use more than...

Страница 7: ...nation 2 A chimney cannot be offset more than 30 degrees from a vertical plane 3 A chimney may run straight up or it may be neces sary to offset it to avoid obstructions 4 The maximum length of an ang...

Страница 8: ...ation or how the chimney system should be run contact your Majestic Fireplaces dealer for assistance Insulating Fireplace Enclosure for Cold Climates If you live in a cold climate it is not required b...

Страница 9: ...he fireplace 3 Slide the rear firebrick back into the left corner behind the end of the left firebrick Push both panels back as far as possible into the left side and corner 4 Swing the right side of...

Страница 10: ...30 Offset Elbow table on Page 6 to determine proper offset and parts required Each offset requires two 2 elbows The second elbow is equipped with support straps It is very important to install the sec...

Страница 11: ...le surfaces in front of the fireplace This Z shaped safety strip is not provided but must be fabricated of metal with each horizontal leg at least 1 inches wide and equal in length to the metal strips...

Страница 12: ...ers provide minimum required air space to chimney pipe for ceiling thickness up to eight 8 inches When combined thickness of ceiling material ceiling joists and flooring material exceeds eight 8 inche...

Страница 13: ...the installation manual provided with the termination cap Locate Chimney Centerpoint on Roof Use same procedure detailed in locating center point of the flue system Drive a nail up through roof at the...

Страница 14: ...n the front standoffs that may be used to attach finish material Fig 23 Finish Wall Finish the wall with material of your choice Do not install a combustible mantel shelf less than 12 305mm from the t...

Страница 15: ...5mm min 1 6 159mm Min 1 FP531 Fig 22 Mantel clearance Header Must be sealed with noncombustible material Surround Face Finished Wall Ledge Bracket Finished Wall Ledge Bracket Combustible Mantel and Tr...

Страница 16: ...Not Place Finishing Material Beyond These Edges or Cover Air Inlets Screen Rail Hearth FP1168 Fig 26 Finishing front of fireplace MA81 Fig 27 Combustible mantel clearances 1 Ref Combustible materials...

Страница 17: ...resistance Rt value of the alternate material employed is greater than or equal to R 1 09 Thermal resistance R or thermal conductiv ity K may be obtained from manufacturer of the material Factors are...

Страница 18: ...85 between decorative noncombustible rigid covering and combustible wall Minimum height and width is 40 x 40 Dimension degree of angle will vary depending on thickness of noncombustible surround facin...

Страница 19: ...pecialty Home Products fireplaces Be sure to have the appliance installed in accordance with building codes Gas connection may enter from either left or right side of the fireplace Locate appropriate...

Страница 20: ...05299 4 Screen Rod two per fireplace 7554181 7554199 20001428 20002790 5 Screen two per fireplace 7554295 20001723 20001723 20005278 6 Screen Pull two per fireplace 5584139 5584139 5584139 5584139 7 P...

Страница 21: ...lable from your local Majestic Fireplaces distributor Should you need additional information beyond what your distributor can furnish contact CFM Specialty Home Products 410 Admiral Blvd Mississauga O...

Страница 22: ...roof Flashing not included For use with Vermont Castings Majestic Products Type 11CF Chimney Systems Used to terminate chimney at top of chase Adapter kit included Flashing not included Used to build...

Страница 23: ...ject to the following conditions and limita tions 1 This warranty is extended only to a Fireplace installed in the continental United States the state of Alaska and Canada only if and so long as the F...

Страница 24: ...CFM Specialty Home Products 410 Admiral Blvd Mississauga Ontario Canada L5T 2N6 905 670 7777 www majesticproducts com www vermontcastings com CFM Specialty Home Products...

Отзывы: