Installation

WARNING: The inverter uses power from both AC and DC  sources. 
Before  beginning  the  installation,  ensure  all  AC  power  (utility/
generator) and any negative and positive battery cables are safely 
disconnected from the inverter.

Refer to Figure 3 for the following steps:

1.  Remove the cover of the conduit box by removing the two #10 - 1/2” 

Phillips screws attaching the cover to the bottom.

2.  Determine the AC and DC wiring thru the conduit box, and then remove 

the appropriate knockouts and attach the corresponding strain reliefs.

3.  On the inverter, remove the two #25 Torx screws that hold the inverter 

cover – located on the inverter’s front side.

4.  Align the conduit box with the front side of the inverter, and then place 

the holding tabs located on the conduit box bottom over the screw open-
ings from the #25 Torx screws removed in Step 3.

5.  Attach the conduit  box to  the inverter using the  two #25  Torx screws 

that were removed from the inverter cover in Step 3.

6.  Secure the conduit box mounting fl anges – preferably to the same mount-

ing surface used for the inverter.

7.  Route the AC and DC wiring through  the appropriate knockouts/strain 

reliefs on the conduit box, and then connect per the inverter’s installa-
tion procedure.

8.  After ensuring all electrical and  hardware  connections  are  correct  and 

secure, attach the cover of the conduit box to the bottom of the conduit 
box using the two screws removed in Step 1.

9.  Apply power to the inverter and test for proper operation.