Step by Step Installation Instructions for Softswitch128
TM
System
6
Step by Step Installation Instructions for Softswitch128
TM
System
6
Step by Step Installation Instructions for Softswitch128
TM
System
Step 2
Panel Mounting
Panel and TUB Mounting
Mounting Guidelines:
• For Indoor Use Only! NEMA, Type 1 enclosure, IP20.
• Mount where ambient temperature is 32 - 104º F
(0 - 40º C).
• Panels weigh up to 150 pounds (68.5 kg). Reinforce
wall structure for weight and local codes.
• Mount panel where audible noise is acceptable.
(Internal relays click.)
• Mount panel so line (mains) voltage wiring is at least 6
feet (1.8 m) from sound or electronic equipment and
associated wiring.
• Mount within 7º of true vertical.
Surface Mounting
• Lutron recommends using 1/4 in. (6 mm) mounting
bolts.
• Allow room for cover. Leave 1 1/2 in. (38 mm)
clearance to each side of panel.
Recess Mounting
• Mount panel from flush to 1/8 in. (3 mm) below
finished wall surface.
• Allow room for cover. Leave 1 1/2 in. (38 mm)
clearance to each side of panel.
Distribution
Panel (if feed
through)
Feed Wiring and
Switch Legs to
loads
Class 2
(PELV) Wiring
Feed Wiring
and
Switch
Legs
Feed Wiring and
Switch Legs to
loads
Class 2
(PELV) Wiring
Feed Wiring
and
Switch
Legs
Front View
Side View
Front View
Side View
Distribution
Panel (if feed
through)
Panel Size
Distance
Mini, TUB16
Standard, TUB48
45 in. (1130 mm)
26 in. (660 mm)
Suggested Mounting Height:
For optimum Controller viewing, mount panels
the following recommended distance from the
floor (measured from floor to bottom of panel):
Содержание Softswitch128
Страница 1: ...R Softswitch128TM Installation Guide S w i t c h i n g S y s t e m Please Read ...
Страница 2: ......
Страница 13: ......
Страница 14: ......
Страница 15: ......