Installation process
Physical installation
process chart
The chart shown below assigns the concurrent installation activities for
each of two installers. The specific activities are listed in the table that
follows.
Physical installation
process table
This table represents the activities required to install a Modular Cell
4.0B primary cabinet with integrated power.
INSTALLER 1
ACTIVITY
NUMBER
#1
#2
#3
#4
#6
#7
#8
#9 #10 #11
#12
INSTALLER 2
ACTIVITY
NUMBER
#2
#5
#7
#5 (CON
’T)
ACTIVITIES
INSTALLER ACTIVITY
ASSIGNMENT
INSTALLER 1
INSTALLER 2
1. Check parts inventory
X
2. Line up cabinet on the cabinet anchor holes
X
X
3. Anchor the cabinet to the surface
X
4. Ground the cabinet
X
5. Install six RF antenna cable jumpers and one GPS antenna
cable
X
6. Install the conduit interface for the T1/E1 and user alarm
cables
X
7. Route the T1/E1 and user alarm cables into the cabinet
X
X
8. Punch down the T1/E1 lines at the EFIM
X
9. Install the conduit interface for the AC utility cable
X
10. Route and connect the AC feed to the terminal block in the
power module
X
11. Turn on and check power
X
12. Clean up
X