background image

www.nationwideplatforms.co.uk

If there is a machine breakdown or if the operator becomes 

incapacitated it may be necessary to perform an emergency rescue 

from the ground. Emergency rescues must be rehearsed routinely.

While every effort is made to ensure that the information provided is accurate and up to date, we are not able 
to guarantee the completeness and accuracy of these instructions and you should therefore not rely on them. 
Nationwide Platforms Ltd accepts no liability for reliance on the contents of this information sheet which has 
been produced as additional GUIDANCE ONLY and is not intended to replace the manufacturer’s manual. You 
should refer to the manufacturer’s manual.
You should not operate this Mobile Elevating Work Platform (MEWP) unless you are suitably trained and fully 
familiarised with its operation and the emergency procedures set out in the manufacturer’s manual. Operating 
plant necessarily involves risk of injury to the person.

Warning

A

B

Emergency Lowering Instructions 

Genie Diesel Boom Lifts

Machine Range: Z4525

•  Will there be a second person in the vicinity of 

the machine to undertake a rescue if required?

•  Have both the operator and rescuer been 

familiarised with the ground controls?

•  Can the rescuer gain access to the ground controls? 

i.e. Ensure that the machine is not parked with the 

ground controls facing a wall or similar obstruction.

•  Is the key in the ground control to allow the rescuer 

to switch power from basket to ground controls?

Before starting work consider the following:

•  It is imperative that an inspection be carried out to 

ensure the lowering of the boom is not hindered by 

obstructions such as steel work, pipes, cables, etc. 

•  If the operator in the cage has been incapacitated 

ensure they will not be put in additional danger by 

operation of the platform. Remember that completing 

a rescue in 4-6 minutes may be critical.

•  If unsure seek help (it may be necessary to carry out 

a mid air rescue).

•  Carefully plan each action before starting to lower 

the platform.

Before attempting to operate any boom functions: