background image

6

Hot water outlet

The next step in the installation process is to connect the hot 
water system piping to the hot water outlet port. The hot 
water supply tapping is located on top of the tank.

A manual shutoff valve should be installed downstream on 
the hot water outlet line as an isolation device in case the 
unit must be disconnected from the system. The shutoff 
valve should be in the closed position and remain so until the 
installation is complete.

Mixing valve

Field supplied.  An anti-scald mixing valve is recommended 
when storing domestic hot water above 115°F.

Aquastat bulbwell

Review the controls for the hot water source equipment.  Some 
equipment or systems designs will require an independent 
aquastat (field supplied) to control the equipment. The 
aquastat may be surface mounted onto the jacket of the 
tank or a nearby surface. The water sensing probe may be 
installed in the 3/8" diameter dry bulbwell supplied with all 
Lochinvar Hot Water Storage Tanks. The equipment may 
employ a water sensing thermistor. The thermistor would be 
installed into the dry bulbwell and wired back to the hot water 
equipment.

2  

Installation

 WARNING

Before making any connections of water 
inlet or outlet to the unit, assure that 
all piping is clean and free of foreign 
material or scale.  This can usually be 
accomplished by “blowing out” the pipe.  
Any foreign material or scale entering the 
unit can adversely affect operation and 
performance.

The two (2) tappings on the lower side of the tank shall 
provide recirculation between the tank and the water heating 
source.  See example piping diagram between a storage tank 
and an indirect gas fired water heater (FIG. 2-1).

Connecting the hot water source

 NOTICE

See the Water Heater’s Installation and 
Operation manual for specific piping 
diagrams that match the inlet / outlet 
water tappings on the tank to the inlet / 
outlet water tappings on the water heater.  
Tapping locations on the water heater 
may vary by product or manufacturer.

Figure 2-1

_Vertical Tank Piping Diagram

FLOW CHECK

VALVE (TYPICAL)

EXPANSION

TANK

THERMOMETER

COLD WATER

SUPPLY

HOT WATER

SUPPLY

BUILDING

RETURN

RELIEF

VALVE

FLOW

SWITCH

WATER

HEATER

CIRCULATOR

STORAGE

TANK

WATER

HEATER

UNION

(TYPICAL)

BALL VALVE

(TYPICAL)

MIXING VALVE

Y-STRAINER

[RECOMMENDED]

IMG00606

 NOTICE

For 

all

 piping connections, the use and / 

or type of joint compound or sealer on the 
joint should be determined by referring 
to local codes, accepted practices, or the 
requirements of the installing contractor.

If the cold water supply to the system is equipped with 
an in-line check valve or backflow preventer, a suitable 
expansion tank must be installed in the cold water supply 
line.

Installation and Operation Manual

  

®

Содержание Lock Temp SJS060

Страница 1: ... are likely to be present WHAT TO DO IF YOU SMELL GAS Do not try to light any appliance Do not touch any electric switch do not use any phone in your building Immediately call your gas supplier from a near by phone Follow the gas supplier s instructions If you cannot reach your gas supplier call the fire department Installation and service must be performed by a qualified installer service agency ...

Страница 2: ... outlet 6 Mixing valve 6 Aquastat bulbwell 6 Piping the relief valve 7 Drain 7 Completing the installation 7 3 OPERATION 8 Startup procedure 8 Shutdown procedure 8 4 INSPECTION 9 5 MAINTENANCE 10 Flushing the tank 10 Revision Notes Back Cover Hot Water Can Scald Water heated to temperatures for clothes washing dish washing and other sanitizing needs can scald and cause permanent injury Children el...

Страница 3: ...WELL FROM WATER HEATER TO WATER HEATER DRAIN VALVE SHIPPED LOOSE HOT WATER OUTLET 23 23 MODEL NUMBER A B C D E F RECIRCULATION TAPPINGS OUTLET SJS060 36 28 14 25 9 25 9 28 1 1 2 NPT 1 1 2 NPT SJS080 69 5 61 75 14 25 9 25 9 24 2 NPT 1 1 2 NPT SJS119 68 3 60 12 14 5 9 5 9 28 2 NPT 1 1 2 NPT WARNING Before using product read and understand instructions Save these instructions for future reference All...

Страница 4: ...when filled to capacity The unit should be mounted to the floor following applicable architectural and local code requirements for the specific installation site NOTE Tanks do not come standard with floor tie downs For all piping connections the use and or type of joint compound or sealer on the joints should be determined by referring to local codes accepted standards and or the requirements of t...

Страница 5: ...Installation 1 The installation must conform to the instructions in this manual and all applicable local state provincial and national codes laws regulations and ordinances Installations in Canada must conform to B149 2 Installation Code 2 Be certain the domestic water supply to the tank has physical and chemical characteristics that fall within the limits shown in Table 2A Where questions exist a...

Страница 6: ...an and free of foreign material or scale This can usually be accomplished by blowing out the pipe Any foreign material or scale entering the unit can adversely affect operation and performance The two 2 tappings on the lower side of the tank shall provide recirculation between the tank and the water heating source See example piping diagram between a storage tank and an indirect gas fired water he...

Страница 7: ...f valve is field supplied All Lochinvar SJS Storage Tanks are equipped with a relief valve tapping on the tank The valve should be piped to a discharge line leading to a suitable drain Piping the pressure relief valve to a suitable drain will prevent both water and heat damage to the unit as well as reduce the risk of injury from released heated water The pipe must be of adequate size to properly ...

Страница 8: ...ow all accepted and recommended procedures when performing installation operation and maintenance procedures to avoid possible injury or death Shutdown procedure 1 Turn off all power to the circulating pump and the hot water source controls 2 Close all valves in the system in the following order the hot water outlet line the recirculation water piping 3 Relieve the pressure where possible 4 After ...

Страница 9: ...ONS To Be Inspected Time Interval Per Manufacturer Specs Weekly Monthly Quarterly Annually Circulating Pump Gauges Pressure Temperature Lines Inlet Outlet Return Pressure Relief Valve Shutoff Valves Manual Temperatures Water Operating Thermometer Interior for Sediment or Scale Flush tank at six 6 month intervals 4 Inspection Installation and Operation Manual ...

Страница 10: ...rical power to the circulating pump and any other tank accessories 2 Close the valve on the hot water outlet on top of the storage tank 3 Ensure that the drain located on the bottom of the tank is routed to a floor drain with adequate capacity to allow the tank to be flushed 4 Open the drain valve and allow the incoming cold water to flush the soft sediment out the bottom of the storage tank Use e...

Страница 11: ...11 Notes Installation and Operation Manual ...

Страница 12: ...CO C11908 reflects the update of chart information in FIG 1 1 on page 3 for SJS080 Revision C ECO C12382 reflects the addition of the CSA Low Lead Content logo Revision D ECO C15671 reflects the addition of the Locating the tank caution on page 5 SJS I O Rev D 07 14 ...