Lightsafe_EDL1PT_Instructions_Rev01
EDL1PT
Circular Flush 3 Hour Non Maintained LED Emergency Fitting
c/w Automatic Self-Test Function
Please read these instructions before installation and retain for the user/maintenance engineer for
future reference.
IMPORTANT NOTE:
The luminaire must be installed by a skilled electrician and to the most current electrical wiring and
building regulations
This product
MUST
be earthed
and
NOT
be subject to an electrical insulation test (500/1000v)
which will not be covered by the warranty
The luminaire should not be modified, if modified this will invalidate any warranties and Firesafe will
not be liable for any damages caused
The person carrying out the installation is to check and verify that the total load on the circuit,
including the rating of the cable, fuse and/or circuit breaker is not exceeded
It is the responsibility of the installer to consider any fire risks and breach in any fire protection
barriers or partitions, and take the appropriate precautions
Emergency lighting should be installed and maintained in accordance with BS5266 and BS EN50172
INSTALLATION
1.
The fitting is supplied with two different colour front bezels, to change the LED lamp bezel this can
be unscrewed from the LED lamp unit.
2.
Ensure the AC mains supply is isolated
3.
Ensure the correct size hole is made in the ceiling
4.
A permanent 230v AC supply is required to the live (L), Earth and neutral (N) terminals to the driver
pack
5.
Connect the supply cables to the appropriate terminals and ensure no loose strands, also ensure
the cable clamp on the driver adequately secures and clamps the cable used
6.
Ensure there is at least 100mm of free space around the luminaire and no insulation is placed on
top of the luminaire or its associated parts
7.
Plug the battery and LED lamp lead to the driver pack ensuring no cables are trapped
8.
Restore the mains supply, the green charge LED should be illuminated
9.
Allow 24 hour to charge the batteries and record the installation date in the log book
10.
After a 24 hour charge period test the luminaire for a full 3 hour duration and record the date of
the commissioning on the battery pack and log book
11.
Subsequent testing should be carried out in accordance with the British/European standards and
recorded in the log book