- 42 -
1. Check that all tubing and wiring have been prop-
erly connected.
2. Check that the gas and liquid side service valves
are fully open.
1. Prepare remote control
Remove the battery cover
by pulling it according to the
arrow direction.
Insert new batteries making
sure that the (+) and (–) of
battery are installed correctly.
Reattach the cover by
pushing it back into position.
NOTE:
• Use 2 AAA(1.5volt) batteries. Do not use
rechargeable batteries.
• Remove the batteries from the remote control if
the system is not going to be used for a long time.
2. Settlement of outdoor unit
Anchor the outdoor unit with a bolt and
nut(ø10mm) tightly and horizontally on a con-
crete or rigid mount.
When installing on the wall, roof or rooftop,
anchor the mounting base securely with a nail or
wire assuming the influence of wind and earth-
quake.
In the case when the vibration of the unit is con-
veyed to the hose, secure the unit with an
anti-vibration rubber.
3. Evaluation of the performance
Operate unit for 15~20 minutes, then check the sys-
tem refrigerant charge:
1. Measure the pressure of the gas side service
valve.
2. Measure the temperature of the intake and dis-
charge of air.
NOTE: If the actual pressure are higher than shown,
the system is most likely over-charged, and
charge should be removed. If the actual pres-
sure are lower than shown, the system is most
likely undercharged, and charge should be
added.
The air conditioner is now ready for use.
Bolt
Tubing connection
Outside ambient TEMP The pressure of the gas side service valve
35°C(95°F)
4.5~5.5kg/cm
2
G(63.9~78.1 P.S.I.G.)
This is performed when the unit is to be relocated
or the refrigerant circuit is serviced.
Pump Down means collecting all refrigerant in the out-
door unit without loss in refrigerant gas.
CAUTION:
Be sure to perform Pump Down procedure with the
unit cooling mode.
Pump Down Procedure
1. Connect a low-pressure gauge manifold hose to the
charge port on the gas side service valve.
2. Open the gas side service valve halfway and purge the
air from the manifold hose using the refrigerant gas.
3. Close the liquid side service valve(all the way in).
4. Turn on the unit's operating switch and start the cool-
ing operation.
5. When the low-pressure gauge reading becomes 1 to
0.5kg/cm2 G(14.2 to 7.1 P.S.I.G.), fully close the gas
side valve stem and then quickly turn off the unit. At
that time, Pump Down has been completed and all
refrigerant gas will have been collected in the outdoor
unit.
PUMP DOWN
3. Ensure the difference between the intake temper-
ature and the discharge is more than 8°C
(Cooling) or reversely (Heating).
4. For reference; the gas side pressure of optimum
condition is as below.(Cooling)
Discharge
temperature
Discharge air
Intake temperature
Содержание LS-K1820CL
Страница 66: ... 66 2 Display Ass y No Model P No Remark 1 18K 24K 26K 6871A30009D 2 LS K1863DL 6871A30009R ...
Страница 67: ... 67 Schematic Diagram Cooling Only Series ...
Страница 68: ... 68 Heat Pump Series ...
Страница 78: ... 78 Memo ...
Страница 79: ...P NO 3828A30033D March 2003 Printed in Korea ...