Cycle
1. Installation (Connecting the piping between indoor and outdoor unit)
–34–
• Installation
(1) Connect the piping between the indoor and
outdoor unit firmly.
– Incorrect connection may cause the leakage and
incomplete vacuuming.
(2) Attach the charging hose (manifold gage) to the
service port.
– Charging hose is necessary to check the pressure
and to inject R22 for leakage test.
– The valve of charging hose must be closed before
being connected.
(3) Inject the 100~300g R22 through the charging hose
opening the valve.
(4) Check the joint part using a gas detector or soapy
water for leakage.
– On checking, the service valve of main service port
must be closed, this test is only for checking whether
pipe connection is ok or not.
(5) If there is no leakage, discharge R22 in piping
completely into tank for retrieving.
– Complete discharge is needed for vacuuming.
– If leakage is found, please fasten the joint more
tightly.
(6) After closing the valve of charging hose,
disconnect the tank and connect the vacuum pump
to charging hose and open the valve again for
vacuuming.
(7) Turn on the vacuum pump until the pressure drops
below 0kg/cm
2
.
(8) After vacuuming, disconnect the vacuum pump and
open the spindle of service port (liquid-side)
slightly for 30 sec and then open the spindle of
(gas side) with hexagonal wrench.
(9) Open the liquid side completely first and then the
gas side fully in order.
Lo
Purge the air
Outdoor unit
Indoor unit
Liquid side
Gas side
Gas cylinder
R22
Содержание LBNK3660BL
Страница 41: ... 41 Electronic control device MAIN P C B ASM ...
Страница 65: ...Memo 65 ...
Страница 66: ... 66 Memo ...
Страница 67: ...P No 3828A20097T January 2005 Printed in Korea ...