INSTALLATION OF INDOOR
Selection of the best location
Install the air conditioner in the location that
satisfies the following conditions.
- The place shall easily bear a load exceeding
four times the indoor unit’s weight.
- The place shall be able to inspect the unit as
the figure.
- The place where the unit shall be leveled.
- The place shall easily connect with the out-
door unit.
- The place where the unit is not affected by
an electrical noise.
- The place where air circulation in the room
will be good .
- There should not be any heat source or
steam near the unit
Ceiling dimension and hanging
bolt location
Install the unit above the ceiling correctly.
Position of suspension Bolt
- Apply a joint-canvas between the unit and
duct to absorb unnecessary vibration.
- Apply a filter Accessory at air return hole.
CASE 1
Confirm the positional relationship between
the unit and suspension bolts.
- Installation the ceiling opening to clean the
filter or service under the product.
INSTALLATION OF INDOOR
Top view
Unit: mm(inch)
Front view
Unit: mm(inch)
Front
Inspection hole
600(23-5/8)X600(23-5/8)
Control box
1000(39)
20(25/32) or more
600
(23-5/8)
600
(23-5/8)
Drainage hole
A
B
C
D
(G)
E
F
body
filter
Joint canvas
Main duct
H
I
J
A B C D E
F (G) H
I
J
18/21 kBtu/h 932 882 355 46 450 30 87 750 163 260
24/36 kBtu/h 1232 1182 355 45.5 450 30 87 830 186 298
42/48/54 kBtu/h 1290 1230 447 56 590 30 120 1006 294 380
Dimension
Capacity
(Unit:mm)