Power-on sequencing (some models)
You can use the power-on sequence function to define a sequence for powering on the PDU outlets. You
can use Telnet and SNMP through the Ethernet port or HyperTerminal through the serial port to configure the
power-on sequence function.
Use the power-on sequence function for the following two scenarios:
• Device dependency There are applications that required the power-on sequence function. For example, a
system includes device A, device B, and device C and requires that device A is powered on first, then
device B, and then device C. If the devices do not follow the required sequence when powered on, the
system will not run correctly.
• Power-on in-rush current In-rush current might be a problem in some applications if you are powering on
multiple devices at the same time. In such applications, the power-on sequence function is required to
power on devices in user-definable sequences to limit in-rush current.
The PDU outlet numbering is shown in the following illustration. The PDU orientation is horizontal with the
Ethernet port on the left.
5
6
2
1
3
4
LAN
2
1
3 4
6
5
7 8
10
9
1112
Ethernet port
The following illustration shows the design and implementation of the power-on sequence function.
To use the power-on sequence function, you must set the following parameters by using either a serial or
Ethernet interface:
• GlobalDelayTimer (range: from 0 - 3600 seconds; data type: integer). All PDU outlets are controlled by this
global timer. If GlobalDelayTimer is not set (equal to 0), the global delay function for all outlets is not
enabled.
Chapter 5
.
Monitoring the power status
31
Содержание 46M4002
Страница 1: ...1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Страница 24: ...16 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Страница 30: ...22 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Страница 34: ...26 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Страница 56: ...48 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Страница 60: ...52 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Страница 62: ...54 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Страница 68: ...60 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Страница 70: ...62 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Страница 74: ...66 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Страница 82: ...Taiwan BSMI RoHS declaration 74 1U C19 and C13 Switched and Monitored PDUs Installation and Maintenance Guide ...
Страница 85: ......
Страница 86: ......