eCO2Boost XS 3
12
Unit cooler volume
Piping length
10.2. CO
₂
charging amount estimation
10.1. CO
2
charging process
1.
Check CO
2
amount for each unit cooler and piping volume from graph (see paragraph 10.2).
2.
Set CO
2
vessel on the weight scale, purge air inside charge tube and 0 setting scale before charging.
3.
Break the vacuum by charging the installation in gas state up to a pressure of 10 bar on all the circuits.
4.
Charge CO
2
without compressor running (liquid state) (charging from suction side service valve).
5.
Compressor start running(push operation SW) if CO
2
charging stop before reaching target weight.
6.
Close service valve after CO
2
weight reaching target amount.
7.
Keep & check cooling operation until unit cooler air or cabinet temperature is reached at target temperature.
8.
Check low pressure until reaching target & operation conditions(both of CO
2
& air side) are stable.
9.
Compare actual high pressure & discharge pressure from the target table (see paragraph 10.3).
10.
Charge more 50g CO
2
if high pressure is lower or discharge temperature is higher than table value.
11.
Continue “5.10” process until operation status within ±0.2MPa in pressure, ±5K in discharge temperature for
each target value.
Содержание eCO2Boost L
Страница 2: ...eCO2Boost XS 3 2 ...
Страница 4: ...eCO2Boost XS 3 4 2 Product diagram ...
Страница 16: ...eCO2Boost XS 3 16 13 Fault Tree Analysis 13 2 Too much cooling 13 1 No cooling ...