Heat Section Installation 

Before installing the electric heat section, check the unit 

rating plate to ensure that the unit meets the job require-

ments, that proper electrical power is available, and that 

proper duct clearances are maintained.

KNOCK OUT EXTENDED WIDTH WHEN USING 

20KW OR 25KW ELECTRIC HEAT

FIGURE 1. Air Handler Electric Heat Knockouts

NOTE

 – 

It is easier to install the electric heat section in-

side the air handler unit before the unit is set and the ple-

num is attached.

1 - 

 Shut off all power to the air handler. More than one 

disconnect may be required. 

2 -  Remove air handler access panel. 
3 -   Remove the electric heat knockout from the air 

handler vestibule panel to accommodate the heater 

being used. Remove the extended width knockout 

to allow for installation of 20kW or 25kW heater (see 

figure 1). 

4 -   Slide the electric heat section into the air handler. 

Be careful that the heating elements do not rub 

against the sheet metal opening when they slide 

into the air handler. The hole(s) on each side of the 

heater line up with holes in the air handler control 

box. Secure the electric heater into place with the 

screws that are provided in the bag assembly. 

Cabinet Modifications for 460 Volt, 3 Ton Models 

Modifications  are  necessary  when  an  ECB27-10F-G  / 

15F-G voltage (460 volt) electric heat section is installed 

in a 460 volt, 3 ton air handler (see figure 2).

ISSUE:

SOLUTION:

Remove the tabs identified below.

Tabs restricting electric

heat section installation.

Tabs on a 460 volt, 3 ton air handler prevent proper installation of the ECB27-10F-G / 15F-G voltage (460 volt)

electric heat section.

FIGURE 2

. Cabinet Modifications 

 WARNING

Electric Shock Hazard. Can cause injury or 

death. Unit must be properly grounded in 

accordance with national and local codes.
Line voltage is present at all components 

when unit is not in operation on units with 

single-pole contactors. Disconnect all remote 

electric power supplies before opening 

access panel. Unit may have multiple power 

supplies.

Circuit Breaker Installation 

1 -   Install the circuit breaker on the air handler deck 

flange. Use the provided six screws to secure the 

circuit breaker (see figure 3).

NOTE

 – 

When applied in the downflow position,

 

the cir-

cuit breakers must be rotated to the UP position

See 

figure 3 and follow the procedure below:

A - Disconnect power to the unit if present.
B - 

Remove  the  screw  and  slide  the  breakers  off  the 

mounting rail.

NOTE

 – 

You may need to remove the wire tie closest to 

the circuit breaker to allow rotation.

Содержание ECB27 Series

Страница 1: ...ing Replace all parts and panels before operating Failure to do so can result in death or electrical shock Electric Heat Section The ECB27 series electric heat section provides field in stalled electr...

Страница 2: ...vided in the bag assembly Cabinet Modifications for 460 Volt 3 Ton Models Modifications are necessary when an ECB27 10F G 15F G voltage 460 volt electric heat section is installed in a 460 volt 3 ton...

Страница 3: ...plate for the specific size of electric heat section that you are installing Discard the unused piece of patch plate see figures 5 and 6 6 Secure the patch plate on the air handler access door IN DOW...

Страница 4: ...B ECB27 5CB ECB27 6CB ECB27 8CB ECB27 9CB ECB27 12 5CB ECB27 15CB ECB27 20CB ECB27 25CB ECB27 10CB 3 Ph ECB27 15CB 3 Ph ECB27 20CB 3 Ph ECB27 25CB 3 Ph SIDE OF UNIT DISCARD BREAK AT THIS POINT DISCARD...

Страница 5: ...ith 1 1 2 inch trade size 1 31 32 inch diameter conduit A conduit reducer washer has been provided if you are installing a smaller sized conduit For single point power supply refer to the nameplate on...

Страница 6: ...using ECB27 heat section adjust the blower speed according to the size of electric heat and air handler unit The minimum blower setting for each air handler size with any heat sections in any applicat...

Страница 7: ...PHASE ELECTRIC HEATERS ONLY STATS Y2 USED ONLY WHEN TWO SPEED COMPRESSOR IS USED HP21 COMMON USED ONLY ON SOME THERMOSTATS USING SERVICE LIGHT OPTION S54 WITH SOME ELECTRONIC THERMOSTATS MAY REQUIRE...

Страница 8: ...Page 8 Unit Field Wiring Diagrams FIGURE 13 Typical Unit Diagram Air Handlers with Constant Torque Motors P Voltage 208 230V 1 Phase 60Hz...

Страница 9: ...Page 9 FIGURE 14 Typical Unit Diagram Air Handlers with PSC Non Communicating Motors P Voltage 208 230V 1 Phase 60Hz...

Страница 10: ...Page 10 FIGURE 15 Typical Unit Diagram Air Handlers with Variable Speed Communicating Motors P Voltage 208 230V 1 Phase 60Hz...

Страница 11: ...Page 11 FIGURE 16 Typical Unit Diagram Air Handlers with Constant Torque Motors G Voltage 460V 3 phase 60Hz...

Страница 12: ...ECB27 5 CB P 538002 01 ECB27 6 CB P 538002 01 ECB27 8 CB P 538003 01 ECB27 9CB P 538004 01 ECB27 12 5CB P 538005 01 ECB27 15CB P 538005 01 ECB27 20CB P 538006 01 ECB27 25CB P 538010 01 ECB27 8 Y 53800...

Отзывы: