The unit must be transported in a VERTICAL POSITION on its metal bedplate profiles. Any other position may
cause serious damage to the machine. When the unit is received, it should be checked to assure that there are
no bumps or other damage, following the instructions on the packaging. If there is damage, the unit may be
rejected by notifying the LENNOX Distribution Department and reporting why the machine is unacceptable on the
transport agents delivery notice. Any later complaint or claim made to the LENNOX Distribution Department, for
this type of anomaly, cannot be considered under the Guarantee.
Sufficient space must be allowed to facilitate placement of the unit.
The unit may be mounted outdoors. There should be NO possibility of flooding if floor mounted.
All the units have Metal Bedplate Profiles.
All INSTALLATION, SERVICE and MAINTENANCE operations
must be carried out by QUALIFIED PERSONNEL.
When positioning the unit, be sure that the Rating Plate will always be visible since this
data will be necessary to assure proper maintenance.
The units are designed to be installed with ducts, calculated by qualified technical staff. The joints to be used
between ducts and the openings to the unit should be Elastic Joints. Avoid the use of BYPASS joints between the
extraction air and input air in both the outdoor and indoor sections. The structure where the unit is placed must
be able to support the weight of the unit during operation.
2.- INSTALLATION
If unloading and placement require the use of a crane, then secure the suspension cables as shown in the figure.
How to hoist the unit
Use
separators
Use
separators
2.2.- UNIT RECEPTION
2.1.- PRELIMINARY PREPARATIONS