background image

Char-log

®

 

Leg

Concrete Footing

Overhead View

Steel “L” Anchor

Next, mix the concrete with water and pour it into the footing holes using half a bag per hole.

While the concrete is still setting up, you can attempt to anchor the windmill stand to the footing 
without the windmill topper. Set the windmill on top of the 4 footings while the concrete is still 
wet. Take the “L” shaped anchors and push it through the hole in the windmill leg and down into 
the wet concrete. Make sure the anchors are in the wet concrete firmly

Allow for 24 - 48 hours of drying time before putting the windmill topper on the base.

First, find a level surface in your area that you want to anchor the windmill to. Depending on 
local soil conditions, it may be necessary for larger and deeper footings. Softer soils may need 
stronger footings.

Then take the post hole digger and remove at least a 6” diameter x 12” deep of soil. 

Ground

Ground

Ground

Remove

6”

12”