4. Operation
164201241-001 Rev. C0
17
1.
Turn the utility disconnect ON. The green lamp should light, indicating power output.
Power will be applied to the cable plant at this time.
2.
If desired, the output voltage can be checked at the cable center conductor seizure
clamp and the cable ground, using a true RMS AC voltmeter.
If operating from an alternative AC power source such as a generator, the generator
must have a high-quality regulated output consistent with a minimum power rating
that is 50% higher (measured in Watts) than the MiniMax power rating.
Once the initial installation and testing are complete, operation is automatic. When the green
indicator lamp is on, the system is operating from the power line. Proper operation and long
system life can be best assured by a regular performance of the following maintenance
steps.
1.
Before opening the housing, inspect it for external damage or tampering, including
the grounding circuit.
2.
Unlock and open the housing.
3.
Inspect the connectors and cable for damage or corrosion.
4.
Close and re-lock the housing.
4.1
Initial Turn Up
NOTE
5. Maintenance