7.5.2.10 Non Meter-Specific Commissioning Voucher
This voucher is typically used to ease the meter installation process by ensuring that the load
remains disconnected and the
tamper
detect sensing switch function disabled (meter
decommissioned
). Once the installation is complete and the number entered, the load switch
closes and the
tamper
detect sensing switch function enabled.
The
non meter-specific
commissioning
voucher number is:
9999 9999 9997 1939
7.5.2.11 Meter-Specific Commissioning Voucher
This is a
meter-specific
voucher but in all other aspects its operation is the same as described in
7.5.2.10.
7.5.2.12 Meter-Specific Decommissioning Voucher
On accepting a
decommissioning
voucher, the meter opens the load switch (load disconnected)
and disables the
tamper
detect sensing switch function.
7.6
Commissioning and Decommissioning the Meter
The function of being able to set the meter into the
decommissioned
/
commissioned
mode offers
several advantages to meter installation personnel.
In the case of the Gemini PLC meter, when setting the meter into the
decommissioned
mode, the
following occurs:
The
load switch
is set into the open state.
The tamper facility is disabled
When setting the meter into the commissioned mode, the following occurs:
The
load switch
operates as normal.
The tamper facility is enabled
The meter‟s
commissioned
/
decommissioned
status can be observed in the
meter state
register
– 11.13.
7.7
Display Total Units or Remaining Credit at the Meter
This option (configurable at the time of manufacture) is provided for installations where the meter has
a local display and is required to be visually read by a meter reader i.e. the only significant reading
required would be the
total units
– not the normal
remaining credit
, which is only of interest to the
customer. Only the meter display will show the total units. The customer interface unit will continue to
reflect
remaining credit
.
The status of this function can be observed in the
meter option register
– 11.15.
7.8
Power Limiting
The power-limiting feature allows utilities to set the maximum load that can be drawn by customers.
The setting can be changed when necessary via a
set power limit
voucher from the prepayment
vending system.
This algorithm is included in the meter‟s software and is implemented as follows: