5 Installation at Site
46 of 116
CHTRa
If the pump feet have not been pinned at the factory, the holes for parallel pins C
must be drilled at the place of installation and the parallel pins fitted.
▪
The other pump set components shall be fastened and pinned as described in the
relevant manufacturer’s product literature.
▪
Have the tightening torques of all fastening bolts and foundation bolts checked
and confirmed by the responsible site management.
▪
Have the alignment/taking-over certificate confirmed by the responsible site
management.
5.19 Installing or connecting the measuring instruments
DANGER
Lack of necessary monitoring and alarm equipment
Failure of pressurised components!
Explosion hazard
Risk of injury in the event that the hot, pressurised fluid handled escapes!
▷
Mount the monitoring and alarm equipment necessary to ensure operating
reliability.
General
▪
Choose a pressure gauge with an adequate measuring range!
▪
Do not remove the screwed plugs of the connection points until immediately
before mounting.
Pressure gauges (if applicable)
▪
Insert the gasket (to ZN16258 (DIN 16258)) and tighten the clamping nut.
Thermometer (bearing)
▪
Insert the seal element. Screw in the thermometer.
Oil sight gauge or constant level oiler (if applicable)
▪
Screw in the oil sight gauge or constant-level oiler including sealing tape or
liquid seal. Lengthening pieces, if required, are included in the delivery.
Resistance thermometer or thermocouple
▪
When installing standard resistance thermometers observe the assembly
instructions.
▪
For the feeler length and the threaded connection required for the respective
measuring point, please refer to the list of measuring points and check the
length at the place of installation.
▪
Insert the seal element. Screw in the resistance thermometer or thermocouple.
▪
Run the electric connecting cables in cable conduits until just before reaching the
measuring point and have them connected by authorised personnel.
Differential pressure monitoring equipment (if applicable)
1. Fasten the differential pressure monitoring equipment to the holder provided
on the baseplate.
2. Fasten the instrument leads at the intended connection points and install them
according to the constraints on site.
3. Run the electric connecting cables in cable conduits until just before reaching
the measuring point and have them connected by authorised personnel.
Содержание CHTRa
Страница 1: ...Process Pump CHTRa Installation Operating Manual...
Страница 112: ...10 Related Documents 112 of 116 CHTRa 10 5 Order specific documents...
Страница 114: ...Index 114 of 116 CHTRa W Warnings 9 Warranty claims 7 Weight 110...
Страница 115: ......
Страница 116: ...KSB SE Co KGaA Johann Klein Stra e 9 67227 Frankenthal Germany Tel 49 6233 86 0 www ksb com 2700 81 03 EN...