9.3 Integrated pilot connections

Nozzle set BR 65–1 40 with NPT thread is required 
for integrated pilots (sizes 165 and 200 on request).

Gas type

order no.

Natural gas

74922638

LPG

74922639

9.4 Gasket sets for reverse flow pressure

For reverse flow pressures of 100 mbar < p < 500 mbar.  

“Gasket set BR XY 500 mbar” contains a mounting 

gasket, a gas housing gasket and a burner tube gas-
ket made of pressure-resistant gasket material. The 
standard gaskets must be replaced with the gaskets 
from the gasket set for reverse flow pressure. The 
gasket sets are available on request. 

10 teCHnICAL DAtA

Gas supply pressure and air supply pressure each 
depend on the use and gas type.

Gas and air pressures:

 

see burner diagrams at www.docuthek.com.
Special gaskets are available on request for air 
pressures of > 100 mbar (39.4 "WC) (e.g. reverse 
flow pressure in the furnace).

Burner flow rate curves:

 

A web app to view the burner flow rate curves is 

available at www.adlatus.org.

Gas types:

 

natural gas, LPG (gaseous), coke oven gas, town 
gas, low calorific value gas and biogas; other types 
of gas on request.

Combustion air:

 

The air must be dry and clean in all temperature 

conditions and must not contain condensate.

overall lengths:

 

100 to 500 mm (3.9 to 19.7 inches) or 50 to 

450 mm (2 to 17.7 inches), length increments: 

100 mm (3.94 inches) (other lengths available on 

request).

Control type:

 

staged: On/Off, 
modulating: constant 

λ

 value.

Flame control:

 

with flame rod (UV control as an option).

Ignition:

 

direct spark ignition; integrated pilot as an option.
Storage temperature: -20°C to +40°C.

Burner body:

 

BIC: GG,  
BICA: AlSi,  
BICW: St + internal insulation.  
Most of the burner components are made of corro-
sion-resistant stainless steel. 

Ambient conditions:

 

-20°C to +180°C (68°F to 356°F) (outside the ther-

moprocessing system); no condensation permitted, 
painted surfaces may corrode.

Maximum furnace temperature:

 1450°C 

(2642°F)

Maximum air temperature:

 

BIC: up to 450°C (842°F),  
BICA: up to 200°C (392°F),  
BICW: up to 600°C (1112°F). 

10.1 Ceramic tube

Material: SI-1500.
Maximum furnace temperature: up to 1450°C 
(2642°F).
Maximum air temperature: up to 600°C (1112°F).
Maximum material temperature: up to 1500°C 
(2732°F).

10.2 ReACH Regulation

applies to BICW only. 
Information pursuant to REACH Regulation No. 

1907/2006, Article 33.  

Insulation contains refractory ceramic fibres (RCF)/
aluminium silicate wool (ASW).  
RCF/ASW are listed in the Candidate List of the 
European REACH Regulation No. 1907/2006. 

11 LoGIstICs

transport

Protect the unit from external forces (blows, shocks, 
vibration).

Transport temperature: see page 15 (10 Technical 

data). 

Transport is subject to the ambient conditions de-

scribed.
Report any transport damage on the unit or packaging 
without delay.
Check that the delivery is complete. 

storage

Storage temperature: see page 15 (10 Technical 
data).
 
Storage is subject to the ambient conditions described.
Storage time: 6 months in the original packaging before 
using for the first time. If stored for longer than this, the 
overall service life will be reduced by the corresponding 
amount of extra storage time.

12 DIsPosAL

Devices with electronic components:

Weee Directive 2012/19/eU – Waste electrical 
and electronic equipment Directive

 

At the end of the product life (number of op-

erating cycles reached), dispose of the pack-
aging and product in a corresponding recycling 
centre. Do not dispose of the unit with the usu-
al domestic refuse. Do not burn the product.  
On request, old units may be returned carriage paid 
to the manufacturer in accordance with the relevant 
waste legislation requirements. 

Содержание BIC 100

Страница 1: ...ust be installed and commissioned in accordance with the regulations and standards in force These instructions can also be found at www docuthek com 1 2 Explanation of symbols 1 2 3 a b c Action Instruction 1 3 Liability We will not be held liable for damage resulting from non observance of the instructions and non com pliant use 1 4 Safety instructions Information that is relevant for safety is i...

Страница 2: ...operation B Natural gas D Coke oven gas town gas G Propane propane butane butane M Propane propane butane butane with mixer L Low calorific value gas F Biogas L integrated pilot R Reduced capacity X X mm length of steel tube as of furnace flange L1 X X mm distance from furnace flange to front edge of burner head L2 X Burner head identifier XE Heat resistant version A Z Construction stage H High te...

Страница 3: ...formation of dust when dis mantling the burner insert and do not damage the surface of the internal insulation 1 2 3 4 Place the burner insert in such a way that the in sulators are protected against damage No burner extension 1 2 3 4 Centre the ceramic tube 5 6 7 Tighten the screws in a crosswise fashion Mounting flange and furnace flange must be flush With burner extension 1 2 3 Centre the ceram...

Страница 4: ... 65 Rp 3 4 Rp 1 1 2 BIC 80 Rp 3 4 Rp 2 BIC 100 Rp 1 Rp 2 BIC 125 Rp 1 1 2 DN 65 BIC 140 Rp 1 1 2 DN 80 BICW 65 Rp 3 4 DN 65 BICW 80 Rp 3 4 DN 80 BICW 100 Rp 1 DN 80 BICW 125 Rp 1 1 2 DN 100 BICW 140 Rp 1 1 2 DN 125 Up to burner size 100 threaded connection as from burner size 125 flanged connection BICA 65 tube connection Threaded connection to DIN 2999 flange dimen sions to DIN 2633 PN 16 Install...

Страница 5: ...ld flange K to air pipe P for air connection LA and use NPT thread adapter H for gas connection GA BIC 125 and BIC 140 H K GA LA P BICW GA LA K P H 14 16 17 3 6 Pilot connections on the BIC L Air connection la Rp 3 8 Gas connection ga as from burner size 65 Rp 1 4 la ga Pilot capacity 1 5 kW 3 7 Installing the burner insert WARNING BICW do not damage the surface of the insulation Avoid the formati...

Страница 6: ...or burner ground to the burn er insert In the case of single electrode operation route the PE wire from the burner insert directly to the terminal on the automatic burner control unit WARNING High voltage risk It is essential that a high voltage warning label be attached to the ignition cable 7 For more detailed information on how to wire the ionization and ignition cables refer to the operating i...

Страница 7: ...erature rises Fine adjustment should be carried out at max furnace temperature and at as high a capacity demand as possible 5 3 Notes on the flow rate curve If the gas density in the operating state differs from that reflected in the flow rate curve convert the pressures according to the local operating state pB pM δB δM δM Gas density reflected in the flow rate curve in kg m3 lb ft3 δB Gas densit...

Страница 8: ... type label are equipped with gas flow adjustment to replace the restrictor in the gas pipe 5 7 Hot air compensation The combustion air pressure pair must be increased in hot air operating mode lambda constant 0 50 100 150 200 250 300 350 400 450 500 550 600 100 150 200 300 250 Air temperature C Air pressure p air The gas pressure is increased by 5 10 mbar The total burner capacity Pgas rises as t...

Страница 9: ...heck the air pressure pair 5 10 Preparing the gas pressure measurement for low fire and high fire 1 Connect all measuring devices for subsequent fine adjustment of the burner Leave the gas supply closed Gas measuring nipple G outside dia 9 mm 0 35 5 11 Burners without gas measuring orifice 1 Read the gas pressure pgas for the required flow rate Q from the enclosed flow rate curve for cold air mbar...

Страница 10: ...with approx 10 turns 3 4 Loosen the lock nut only 5 Q Set flow rate Q 6 7 8 Gaszufuhr öffnen 9 Ignite the burner The safety time of the automatic burner control unit starts to elapse 10 If no flame forms check and adjust the gas and air pressures of the start gas adjustment 11In the case of operation with bypass e g when using an air gas ratio control check the bypass nozzle and adjust if required...

Страница 11: ...r flow rates if possible De termine the lambda value and readjust the settings if required 6 5 Tightness test DANGER Escaping gas Danger from a leakage at the gas connections Check the gas connections on the burner for leaks immediately after commissioning the burner 1 2 3 4 Avoid condensation due to the furnace atmos phere entering the burner body While the burner is switched off at furnace tempe...

Страница 12: ...ried out by authorized trained personnel only DANGER Risk of burning Outflowing flue gases and burner components are hot We recommend that all the gaskets removed during maintenance work be replaced The appropriate gasket set is available separately as a spare part 1 Check the ionization and ignition cables 2 Measure the ionization current The ionization current must be at least 5 µA and must not ...

Страница 13: ...lectrode from ground pin or gas nozzle 2 0 5 mm 0 08 0 02 2 0 5 mm 0 08 0 02 inch 6 When the furnace chamber has cooled down check the burner tube and burner block through the furnace flange Replace the gas housing gasket 7 8 9 10 Tighten burner insert in a crosswise fashion BIC A 50 to 100 with max 15 Nm 11 lb ft BIC 125 to 140 with max 30 Nm 22 lb ft 11 Connect the system to the electrical power...

Страница 14: ...ner is adequately grounded Note the automatic burner control unit operat ing instructions No ignition spark is created Check the ignition cable Check the voltage supply and wiring Check whether the burner is adequately grounded Check the electrode see page 12 7 Maintenance Defective insulator on the electrode ignition spark jumps over incorrectly Check the electrode Burner performs a fault lock ou...

Страница 15: ...corro sion resistant stainless steel Ambient conditions 20 C to 180 C 68 F to 356 F outside the ther moprocessing system no condensation permitted painted surfaces may corrode Maximum furnace temperature 1450 C 2642 F Maximum air temperature BIC up to 450 C 842 F BICA up to 200 C 392 F BICW up to 600 C 1112 F 10 1 Ceramic tube Material SI 1500 Maximum furnace temperature up to 1450 C 2642 F Maximu...

Страница 16: ...lfilled RoHS II 2011 65 EU The partly completed machine may only be com missioned once it has been established that the machine into which the product mentioned above is to be incorporated complies with the provisions of the Machinery Directive 2006 42 EC Elster GmbH 14 CERTIFICATION 14 1 Eurasian Customs Union The products BIC meet the technical specifications of the Eurasian Customs Union 14 2 C...

Отзывы: