Connecting the Synchronization Unit to AC
mains, ground and ethernet
The Synchronization Unit must be connected to AC mains, and it must be properly
grounded.
Prerequisites
You must be equipped with a standard set of tools. This tool set must comprise the
normal tools for electromechanical tasks. This includes different screwdriver types,
pliers, adjustable spanners, etc. Tools and consumables for electronic work may also be
required, such as a cable stripper, a soldering iron, etc. Each tool must be provided in
various sizes. We recommend that all tools are demagnetized to protect your equipment.
Depending on the chosen installation method, additional tools may be required.
Context
The mains voltage for the unit is 110 to 240 VAC. It is connected to the vessel mains or
to an uninterruptible power supply (UPS). The unit is also connected to vessel ground.
Two cables are used.
• AC mains cable: This cable is supplied with the K-Sync delivery.
• Ground cable: The ground connection is made using a thick stranded (or yellow/green)
cable making a solid connection between the cabinet and the bulkhead. This cable is
supplied with the K-Sync delivery.
• Ethernet cable: This cable must be provided by the shipyard/customer. If the length
of the Ethernet cable exceeds approximately 60 metres, it is recommended to use an
Ethernet switch to maintain the signal strength.
Observe the following connectors on the rear side of the K-Sync unit:
Figure 5
Rack mounted version connectors
1
Connector for 110 to 240 Vac power cable
2
Connector for RJ45 Ethernet cable
Содержание K-Sync
Страница 6: ...6 342741 B KONGSBERG K Sync ...
Страница 49: ...342741 B 49 Cable layout and interconnections ...
Страница 71: ......
Страница 72: ... 2021 Kongsberg Maritime ...