2. SITE PREPARATION
ROUGH-IN PLUMBING
Turn off the water supplies.
Install or relocate the supplies as necessary to conform to
the roughing-in dimensions.
NOTE: If the bath or foot bath has already been installed,
be sure to cover it to prevent damage before you proceed.
Inspect the waste and supply tubing for damage. Replace
if necessary.
SUPPORT FRAMING – K-1096 MODEL
ONLY
Determine the installation location of the valve,
showerhead, and spout. Install the support framing as
required. IMPORTANT! Secure the bath and shower
piping to the support framing.
Proceed to Fig. #3.
Fig. #1
10”
4”
72” – 78”
TO FLOOR
(TYPICAL)
SUPPORT FRAMING – K-1097 MODEL
ONLY
Determine the installation location of both valves, the
showerhead, and the spout. Install the support framing as
required. IMPORTANT! Secure the bath and shower
piping to the support framing.
Proceed to Fig. #4.
Fig. #2
10”
4”
72” – 78”
TO FLOOR
(TYPICAL)
48” TO FLOOR
(SHOWER ONLY)
3. PRE-INSTALLATION PROCEDURES – K-1096 MODEL ONLY
CAUTION: Risk of product damage. Remove
the aspirator, plaster guards, and valve units before
you apply heat to the yoke.
Remove the valve units, plaster guards, and the aspirator
from the yoke.
Proceed to Fig. #5.
Fig. #3
Valve Unit
Yoke
Aspirator
Plaster