Appendix A Generator Selection and Wattage Requirements
General Wattage Requirements
Consider the total wattage requirements (lights, motors,
appliances) when selecting a generator set, or when
sizing wattage usage in which available space and
construction limit the size of the generator set.
Motor Loads
When figuring generator set capacity requirements for
loads that include electric motors, consider the high
current demanded by the motors during startup. The
inrush or starting current is typically 2 to 3 times higher
than that required when the motor reaches normal
operating speed. Allow a reserve for inrush demands
plus other loads that could be on the line as the electric
motor starts. Use Figure 1 as a guide when selecting
generator set capacity requirements involving motor
loads.
Motor
HP
Starting
(Inrush)
Watts
Running
Watts
1/4
750
330
1/3
1000
400
1/2
1500
600
3/4
2000
750
1
3300
1100
2
4000
2000
3
5000
3000
Figure 1
Motor Requirements
Appliance Loads
Generator sets often furnish AC for appliances such as
TVs, stereos, and electric water heaters. Except for the
resistance-type loads such as the water heater, the
requirements for appliances are usually low. Do not
overlook
such
loads
when
figuring
the
total
requirements. Allow a reserve capacity for anticipated
appliance loads to avoid overloading a generator set.
Lighting Load
To calculate the lighting load, add the wattage of each
generator set-operated lamp. Note that not all of the
lights or lamps are on the generator set AC
circuit—some are DC powered by a 12-volt battery.
Ensure that the calculated total wattage includes only
lights actually on the generator set AC circuit.
Air Conditioners
The starting characteristics of air conditioners vary
greatly—for example, one 12,000 Btu unit has lower
starting requirements than a 10,000 Btu unit of another
variety. When using only one unit, there is usually no
starting problem provided that the lighting and appliance
load is not too high when starting the generator set.
Simultaneous starting of two air conditioning units,
however, can present problems if the generator set
capacity is marginal. Because of the variation in starting
characteristics among air conditioners, this publication
makes no statements regarding multiple-motor starting
capabilities of the generator set covered. Consider
delayed starting or the use of easy-starting devices on
air conditioner units whenever simultaneously starting
more than one motor.
See Figure 2 for typical air conditioner requirements.
The requirements vary among different manufacturers.
Air Conditioner Size (Btu)
7,000
9,000
12,000
16,000
24,000
Voltage
115
230
115
230
115
230
115
230
230
Full load amps
9.3
4.8
9.9
5.0
11.8
6.3
16.3
8.0
11.6
Rated load amps
7.7
4.0
7.0
3.5
8.9
4.8
13.0
6.2
10.2
Locked rotor amps
34.0
20.0
40.0
20.0
50.0
31.0
75.0
36.0
56.0
Starting (inrush) watts
3910
4600
4600
4600
5750
7130
8630
8280
12,900
Running watts
886
920
805
805
1020
1100
1500
1430
2350
Figure 2
Typical Air Conditioner Requirements (60 Hz)
Содержание 7ER
Страница 1: ...Commercial Mobile Generator Sets Model 7ER TP 6034 10 02a Installation...
Страница 2: ......
Страница 4: ...TP 6034 10 02 Table of Contents Notes...
Страница 10: ...VI Safety Precautions and Instructions TP 6034 10 02 Notes...
Страница 12: ...2 Introduction TP 6034 10 02 Notes...
Страница 16: ...6 Cooling System TP 6034 10 02 Notes...
Страница 27: ...Installation Drawing 17 TP 6034 10 02 Section 7 Installation Drawing ADV 6450 E Figure 7 1 Dimension Drawing...
Страница 28: ...TP 6034 10 02 18 Installation Drawing Notes...
Страница 36: ......
Страница 37: ......
Страница 38: ......
Страница 39: ......