Page 2 of 2
3940 Dr. Martin Luther King Drive
St. Louis, MO 63113
P/N KIL00921429 FORM NO. K1429 01/14 ERO-6-01-14
DIRECTION FOR INSTALLATION
WARNING
: Electrical power supply MUST BE
OFF
Before and during installation and maintenance
Wiring Instructions
(Figure 1)
1. Run supply wire (by others) to fixture.
2. Loosen the six clamps (1). Swing the door frame
(2) away.
3. Remove screws (3} from barrier (4) and remove
barrier.
4. Make wiring connections.
CAUTION
: Insulate all wire connections with
NEC approved wire nuts.
5. Replace barrier (4) and securely tighten with
screws (3).
6. Install lamp (by others).
7. Close door frame (2) and close clamps (1).
To Change Line Voltage on Quad Tap
Ballasts: (120v thru 277v)
1. Open Door Frame (2)
2. Remove screws (3) from barrier (4) and remove
barrier.
3. The black line lead marked “Line” is factory
connected to the 277 volt lead. Disconnect from
277 volt and connect to the desired voltage.
CAUTION:
Insulate the 277volt wire with an
NEC approved wire nut.
4. Replace barrier (4), tighten screws (3) and install
lamp.
5. Close door frame (2) and clamps (1).
Floodlight Aiming:
(See Figure 1)
1. Loosen Bolts (5)
2. Aim the floodlight to the desired position.
CAUTION:
To maintain restricted breathing
properties, a seal must be provided on all
conduit or cable entries of restricted breathing
luminaires.
Figure 1