DIRECTION FOR INSTALLATION

WARNING

: Electrical power supply MUST BE 

OFF

Before and during installation and maintenance

Wiring Instructions

 (Figure 1)

1.  Run supply wire (by others) to fixture.

2.  Loosen the six clamps (1). Swing the door frame 

(2) away.

3.  Remove screws (3} from barrier (4) and remove 

barrier.

4.  Make wiring connections.

CAUTION

: Insulate all wire connections with 

NEC approved wire nuts.

5.  Replace barrier (4) and securely tighten with 

screws (3).

6.  Install lamp (by others).

7.  Close door frame (2) and close clamps (1).

To Change Line Voltage on Quad Tap 

Ballasts: (120v thru 277v)

1.  Open Door Frame (2)

2.  Remove screws (3) from barrier (4) and remove 

barrier.

3.  The black line lead marked “Line” is factory 

connected to the 277 volt lead. Disconnect from 

277 volt and connect to the desired voltage.

CAUTION:

 Insulate the 277volt wire with an 

NEC approved wire nut.

4.  Replace barrier (4), tighten screws (3) and install 

lamp.

5.  Close door frame (2) and clamps (1).

Floodlight Aiming:

 (See Figure 1)

1.  Loosen Bolts (5)

2.  Aim the floodlight to the desired position.

CAUTION: 

To maintain restricted breathing 

properties, a seal must be provided on all 

conduit or cable entries of restricted breathing 

luminaires.

Figure 1